Labour time comparison for Cablofil against traditional tray
  Traditional installation Cablofil installation 
  Time perTotal Time perTotal
  unit (hrs)(hrs)unit (hrs)(hrs)
900 mm HD ladder120 m1.583189.960.7488.8
Brackets800.75800.7580
90° bend31.0333.0990.962.88
45° bend11.0331.0330.960.96
Tee41.3335.33214
Crossover01.5010
450 mm HD tray120 m0.56667.920.36844.16
Brackets800.5400.540
90° bends30.5331.5990.481.44
45° bends10.5330.5330.480.48
Tee40.7663.0640.753
600 mm HD 3c tray120 m0.8960.4857.6
Brackets800.6480.648
90° bends30.6661.9980.581.74
45° bends10.6660.6660.580.58
Tee41.14.40.853.4
CF54300 wire tray120 m0.24929.880.24929.88
Brackets800.33326.640.33326.64
90° bends30.2840.8520.2840.852
45° bends10.2840.2840.2840.284
Tee40.3661.4640.3661.464
 Total 602.724 436.16
Information provided for cost analysis on a shopping centre project (December 2005)