Keep up to dateChanges at a glance | ||
Key differences between the existing BB87 and the new requirements in BB93 compiled by Adrian James of Adrian James Acoustics | ||
BB87, 1997 | BB93, 2002 | |
Internal ambient noise levels | Previously called background noise levels, which includes noise from teaching activities in adjacent spaces in addition to the indoor ambient noise from internal and external noise sources identified in BB93 | The indoor ambient noise levels in Table 1.1 of BB93 do not include noise from teaching activities in neighbouring rooms, which is addressed through specification of sound insulation. They include all other noise from internal and external noise sources except noise associated with classroom activities |
Maximum indoor levels | Guidance was given that noise from aircraft and trains should not exceed 55 dB LA1 in teaching classrooms | It is now a requirement that noise from individual noisy events in certain rooms including classrooms should not regularly exceed 55 dB LA1,30mins |
Sound insulation between rooms | Requirements for weighted level of difference Dw are given in terms of a matrix as a function of noise tolerance and activity noise levels | The sound insulation requirements are in some cases more onerous than in BB87. Use of doors communicating directly between classrooms is generally impracticable because these reduce sound insulation, Dw replaced by similar DnT (Tmf,max) |
Sound insulation between rooms and corridors | Dw quoted between rooms and corridors, but was not reproducibly measurable in practice because of the irregular dimensions of the corridors | Requirements are given in Rw (weighted sound reduction index) for walls and doors, and there is a separate requirement for ventilators. Compliance has to be by calculation rather than measurement |
Impact sound insulation | No requirements | New requirements for impact sound insulation of floors over sensitive rooms (see page 8) |
Reverberation times of rooms | Definition of Tmf was mean of 500 and 1000 Hz values | Definition of Tmf changed to mean of 500, 1000 and 2000 Hz values, which means there are limited permissible increases at lower frequencies. Some changes to room descriptions and values |
Absorption in corridors, entrance halls and stairwells | No requirement | Requirements in terms of areas of sound absorbent material, as defined in Section 7 of the new Approved Document E |
Open-plan spaces | No requirement | Use of open-plan spaces for simultaneous teaching of several classes is strongly discouraged. If there is a real demonstrable need for such spaces, detailed acoustic modelling is needed to demonstrate that a Speech Transmission Index (STI) of 0.6 or above will be achieved |
Design checks | School designers were left to self certify compliance with the standards | School designers will have to submit information to satisfy building control bodies that the designs conform to the above requirements. Alternative criteria may be considered by Building Control bodies but must be fully and formally justified |
Commissioning | No requirement | It is recommended that the client should include a requirement for acoustic testing in the building contract. The Building Control body may also request such a test |
Footsteps on the classroom floor: | |
Maximum floor-impact sound levels | |
Type of room | Maximum weighted BB93 standardised impact sound pressure level L'nT (Tmf,max),w dB |
Nursery school playrooms | 65 |
Nursery school quiet rooms | 60 |
Primary school: classrooms, class bases, general teaching areas, small group rooms | 60 |
Secondary school: classrooms, general, teaching areas, seminar rooms, tutorial rooms, language laboratories | 60 |
Open-plan spaces | |
Teaching areas | 60 |
Resource areas | 60 |
Music rooms | |
Music classroom | 55 |
Small practice/group room | 55 |
Ensemble room | 55 |
Performance/recital room | 55 |
Recording studio | 55 |
Control room for recording | 55 |
Lecture rooms | |
Small (fewer than 50 people) | 60 |
Large (more than 50 people) | 55 |
Other rooms | |
Classrooms designed specifically for use by hearing impaired pupils | 55 |
Study room (individual study, withdrawal, remedial work, teacher preparation) | 60 |
Libraries | 60 |
Science laboratories | 65 |
Drama studios | 55 |
Metalwork/woodwork classrooms, resource/light craft and practical work | 65 |
Assembly halls, multi-purpose halls (drama, PE, audio/visual presentations, assembly, occasional music) | 60 |
Audio-visual, video conference rooms | 60 |
Atria, circulation spaces used by pupils | 65 |
Indoor sports hall | 65 |
Gymnasium | 65 |
Dance studio | 60 |
Swimming pool | 65 |
Interviewing/counselling rooms, medical rooms | 60 |
Dining rooms | 65 |
Ancillary spaces | |
Kitchens* | 65 |
Offices*, staff rooms* | 65 |
Corridors*, stairwells* | 65 |
Coats and changing areas* | 65 |
Toilets* | 65 |
* This applies only to teaching and learning spaces and is not intended to cover administration and ancillary spaces. For these areas the values are for guidance only. |