- News
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- Building the Future
- Jobs
- Data
- Subscribe
- Events
2024 events calendar
Explore nowBuilding Awards
Keep up to date
- Building Boardroom
The contractual time limits on issuing payment and pay less notices are generally pretty tight – be mindful of your obligations or risk becoming liable for payment in full
Recent judgments from the Technology and Construction Court have reiterated that so-called smash-and-grab claims are not going away and remain an ever-present concern for any paying party to a construction contract.
Briefly, a smash-and-grab claim arises when a notified sum has arisen under a construction contract and the paying party fails to make payment of that notified sum beyond the final date for payment. Such claims typically arise when an application for payment is not suitably addressed by way of a corresponding payment and/or pay less notice, in which case the paying party must make payment of the notified sum in full. It is therefore imperative that paying parties understand their payment obligations under construction contracts so they can ensure appropriate notices are issued in time.
Pursuant to the Construction Act (as amended), all construction contracts must contain:
…
You are not currently logged in. Subscribers may LOGIN here.
SUBSCRIBE for UNLIMITED access to news and premium content
A subscription will provide access to the latest industry news, expert analysis & comment from industry leaders, data and research - including our popular annual league tables. You will receive:
Get access to premium content subscribe today