Keep up to dateBy Elizabeth Hopkirk2020-10-13T05:00:00
Artelia initially said re-tendering job to overcome £2m budget deficit was not the solution – before performing a ‘volte-face’
The Grenfell Tower refurbishment project would fail unless a fundamental review of its scope was carried out, a consultant working for the client warned at an early stage.
Cost consultant Artelia said re-procuring the main contractor in a bid to overcome a £2m budget shortfall was not the right solution because replacing Leadbitter would “incur additional time and expense” and there was no guarantee another contractor would be better.
Existing subscriber? LOGIN
Stay at the forefront of thought leadership with news and analysis from award-winning journalists. Enjoy company features, CEO interviews, architectural reviews, technical project know-how and the latest innovations.
Get your free guest access SIGN UP TODAY
Subscribe to Building today and you will benefit from:
View our subscription options and join our community