  • Heron tower
    Features

    Spotlight: impact of tower construction

    2011-10-21T00:00:00Z

    London is a rare area of growth, says Brian Moone, and the projects coming back on line include large and complex towers. Developers and suppliers had better plan early to avoid logjams

  • Lead times
    Features

    Lead times July-Sept 2011

    2011-10-21T00:00:00Z

    Although lead times remain overwhelmingly stable, growth in tower construction in London will affect capacity in steel fabrication, vertical transportation and cladding.

  • Fukushima plant
    Comment

    Spotlight: Impact of natural disasters

    2011-07-08T00:00:00Z

    To make sure your business doesn’t get hit hard by fluctuating lead times, you need to understand how international natural disasters could affect you - and where they are

  • leadtimesjuly
    Features

    Lead times April - July 2011

    2011-07-08T00:00:00Z

    The earthquake in Japan has had a negative effect on electronic control equipment and the steel market is fluctuating but enquiries are up and lead times remain stable. Brian Moone of Mace reports

  • Features

    Spotlight: Sustaining lead times

    2011-04-08T00:00:00Z

    Lead times are the best way to put yourself ahead of the market and stay competitive in these tough economic times, says Brian Moone. But how do you sustain this once demand picks up?

  • Features

    Lead times: January-March 2011

    2011-04-08T00:00:00Z

    Despite some components being harder to find and enquiries up, lead times remain overwhelmingly stable, with only two sectors reporting an increase in the last quarter. Brian Moone of Mace reports

  • The main contractor on Chatham Maritime went bust half way through the project
    Features

    Spotlight: When contractors fail

    2011-02-04T00:00:00Z

    The downturn has put many contractors out of business, says Brian Moone. What impact is this likely to have on project lead times?

  • /i/w/a/052_BUILDING05v2_2.jpg
    Features

    Lead times: Oct 2010 - Dec 2010

    2011-02-04T00:00:00Z

    The overwhelming stability of lead times continues, and despite reports of busier order books from clients looking to reduce costs, the next six months look equally flat. Brian Moone of Mace reports

  • Lead times
    Features

    Lead times: July-September 2010

    2010-10-21T18:11:00Z

    The reported increase in enquiries failed to convert to orders, and lead times are overwhelmingly stable this quarter. The next six months look quieter still. Brian Moone of Mace reports

  • Features

    Lead times - April to June 2010

    2010-07-09T00:00:00Z

    An increase in reported enquiries in many trades has not yet been converted to orders, but lead times are already creeping up in four areas compared with only one last quarter

  • Features

    Lead times January-March 2010

    2010-04-09T00:00:00Z

    It looks as though the industry may be turning the corner. Most contractors are reporting an increase in enquiries and for the first time in a long time, a package actually increased. Brian Moone of Mace reports

  • Biomass boiler: 25-40 weeks
    Features

    Spotlight on sustainability

    2009-04-03T00:00:00Z

    Lead times may have levelled out, but if you are commissioning the latest green technologies there could still be a bit of a wait. Brian Moone of Mace gives an idea of what to expect

  • Features

    Lead times: January-March 2009

    2009-04-03T00:00:00Z

    If you want to know about the latest changes to lead times – well there are hardly any. Only two categories have altered, and the situation looks set to stay that way

  • Features

    Lead times: November 08 - January 2009

    2009-02-06T00:00:00Z

    Unsurprisingly, a weak economy has led to a reduced workload for many contractors, a few of whom are dropping lead times to a level not seen since 2003

  • Features

    Lead times May-July 2008

    2008-07-11T00:00:00Z

    Four packages have gone down this week and four have gone up, as the downturn pushes from one end and the steel shortage from the other. Brian Moone of Mace reports the numbers

  • Features

    Lead times February-April 2008

    2008-04-04T00:00:00Z

    Only six packages reported any change this quarter as work loads stabilised, says Brian Moone of Mace. Overleaf, Mace Business School examines the skills crisis

  • Features

    Lead times November 2007-February 2008

    2008-02-15T00:00:00Z

    For the first time since the construction boom began, lead times seem to be returning to normal, says Brian Moone of Mace.

  • Features

    Lead times July-October 2007

    2007-10-26T00:00:00Z

    There were no significant changes to lead times for materials this quarter, indicating that the market is levelling out, says Brian Moone of Mace. Overleaf, he turns the spotlight on tall buildings

  • Features

    Lead times January-June 2007

    2007-07-06T00:00:00Z

    Increased lead times for eight construction packages have been counterbalanced by reductions in eight others, reports Brian Moone of Mace Business School.

  • Features

    Lead times October-December 2006

    2007-02-16T00:00:00Z

    Most lead times are holding steady in the latest quarterly update by Tony Gale of Mace. Overleaf, Gordon Malcolm from the Museum of London Archaeology Service and Paul Barker of Gardiner & Theobald examine archaeological digs on construction sites