Keep up to dateBy Brian Moone2019-10-21T05:00:00
The past quarter has again shown little movement, with lead times static for all but three packages
Rotary piling lead times remain at seven weeks with no change anticipated over the next six months. Precast piling lead times remains at four weeks, with no change in lead times expected over the next six months. Concrete works lead times remain at 10 weeks; enquiry levels and workload remain static and contractors do not anticipate any change over the next six months. Structural steel frames lead times have increased by two weeks to 17 weeks with future order levels unchanged.
…
You are not currently logged in. Building Boardroom Members and Subscribers may LOGIN here.
to read this report now, plus have unlimited access to:
Alternatively…
to gain access to building.co.uk for the latest news, expert analysis & comment from industry leaders, plus data and research.
Already a Boardroom member? Log in here.