Battersea Power Station’s redevelopment has not had an easy time of it lately, with profit margins plummeting and costs soaring. The development company behind the scheme speaks exclusively to Building about the scale of the problems

A political row over affordable housing on the gargantuan multibillion-pound Battersea Power Station redevelopment scheme has given the world a glimpse of the problems facing the project. Planning documents submitted to support the developer Battersea Power Station Development Company’s attempt to reduce provision of affordable homes revealed the expected profit margin (known as IRR) on the 4,000-home project has more than halved from 20% to 8% since it started, as a result of a combination of a falling prime sales market and big cost rises.

For months, rumours of huge construction problems have swirled round the project, which is on site in three enormous phases totalling more than £2bn of construction work. The head of Wandsworth’s planning committee described the scheme as being in “serious financial trouble”, before later altering his online statement to say it was – merely – “facing significant challenges”.

Now it’s time for Rob Tincknell, chief executive of Battersea Power Station Development Company, speaking exclusively to Building, to put his side of the story – and lay bare the scale of the project’s issues.

“This isn’t called the Everest of real estate because it’s easy. It is arguably the toughest project in the world, and the evidence is that it’s sat here for 35 years. And I’m sure that many developers who are still licking their wounds after being shot out the other end would agree.”

Here Tincknell lifts the lid on the scale of construction challenges facing the scheme, where costs have escalated by at least £400m on the rebuilding of the power station alone. Speaking for the first time since the affordable housing provision row returned the job to the spotlight, he does not rule out that the cost of this vital Phase 2 part of the wider regeneration project, originally estimated at £750m, could even end up doubling. However, he also tells Building why – “despite its financial performance” – the scheme’s financial backers are utterly committed to finishing the job.

Rob Tincknell

Source: Battersea Power Station Development Company

Rob Tincknell: Battersea has involved ‘huge, huge, huge’ numbers

Out of the ordinary

Very little about the rebuilding of Battersea is ordinary, or, seemingly, even straightforward. From the decision to rebuild the iconic power station chimneys before the rest of the building; to the provision of an on-site hospital for site workers; to the aquifer running beneath the power station itself, which meant sinking piles 26m down to hit foundable rock; to the construction schedule for the £400m, 865-home first phase of flats that required contractor Carillion to hand over 30 apartments every week.

Tincknell has made “don’t do ordinary” into his team’s motto and remains clearly proud of what is being achieved - with residents moving into the first phase now, and the promised shops and community facilities springing to life. He thinks criticism of the development itself is misplaced. “It’s all about creating an amazing new place for London,” he says.

“When this site went on the market [in 2012], there were four to five bids and, apart from Chelsea Football Club, every single one of them was more or less ‘knock down the power station and build rows and rows and rows of residential’.

“Now that is not the answer to this site – a new town centre for the whole of Nine Elms is the absolute right thing to do. [We’re] bringing jobs, bringing a new cultural capital for London, capitalising on the river, the heritage […] having a mixed community. It’s not easy. Doing the right thing isn’t necessarily the easiest thing.”

You can say that again. Because, back on the business side of the construction hoardings, all is far from rosy. Tincknell admits the construction cost overruns have been, simply, “vast”. Most of the pain, he says, has come from the job to rebuild the power station itself, originally estimated at £750m, the majority of which is being carried out by Skanska. Last year Tincknell admitted the contract price had risen to £1.15bn, but it was indicated then that this was due to incorporating design changes and increases in Skanska’s scope of work.

Battersea Power Station works 2 210717 issue

Source: Battersea Power Station Development Company

Progress on site at Phase 2, where the cost of redeveloping the power station could exceed £1.15bn

Big changes

So, what has happened? Tincknell says it’s a combination of the hot market for construction, a much weaker pound making materials (60% of which come from Europe) more expensive, and – most of all – a gargantuan dollop of unforeseen site problems. The cost of rebuilding the chimneys, for example, was more complicated than anticipated, rising from £28m to £48m.

The cost of the underground energy centre between the power station and the river quadrupled from £17m to £62m. Most extraordinarily, after initial surveys based on limited access to the building put the cost of dealing with asbestos at just £190,000, the reality was several orders of magnitude tougher, and asbestos costs soared 200-fold to £44m. Tincknell said: “pretty much we’ve had to scrub the entire building with a toothbrush”.

He says: “These things have been much more challenging than the entire team, everybody associated with the project, thought they would be. These are big, big changes.

“There are blocks of concrete in the ground the size of this room which have been challenging to remove. There’s an aquifer under the power station that as we’ve excavated down we realised the piles needed to be longer, bigger […] The upshot is we’ve literally spent £400m [just] preparing the building for regeneration.

“The whole budget started off at £750m, it’s then been reported it went to £1.15bn – and it’s now north of that figure. Those have been huge, huge, huge numbers.”

There’s a reason why Tincknell can’t give a final cost. This is that, three years after Skanska was chosen to rebuild the power station, no contract has ever been signed. Tendered as a two-stage, lump sum, design-and-build contract, the sheer volume of changes means the second stage has never been finalised and the contract remains officially “at large” in contract law terminology.

This is despite the fact work has clearly progressed some distance, with Tincknell saying £400m of subcontracts have been placed and “several hundred million pounds more” have been tendered. However, other major packages, such as M&E, have not yet been tendered. To put this problem in perspective, Tincknell claims that even Carillion’s £400m Phase 1 contract was the largest ever let in the UK by a private developer. Phase 2 could be three times that size (see Battersea’s phases, below).

“We’re all working together very hard, tendering packages, day and night, doing a lot of value engineering to get costs in the right position that we can all sign up to and move forward together,” he says. “That’s quite close, but […] it’s still being agreed.” Could it even end up being double the original £750m estimate? “I’m not going to say.” He pauses. “Hopefully not.”

About-turn

Tincknell admits this experience was behind the recent about-turn in approach on the 1,300-home Phase 3. This was originally tendered as a two-stage, lump sum contract, with French contractor Bouygues picked as preferred bidder, but Bouygues has now departed the job and Battersea has brought in Sir Robert McAlpine to build it on a construction management basis.

“Phase 3 was at an earlier stage [than Phase 2], and it made more logical sense to convert that back to a construction management process,” Tincknell says, admitting the risk premium Bouygues was looking to add onto the price was “one of the factors” in the decision. “Contractors, like most businesses, are just trying to avoid risk at the moment, because you don’t know what’s going to happen around the corner.” Of Bouygues specifically, Tincknell simply says “we just mutually decided it just wasn’t right for them and it wasn’t right for us. There’s no blood in the water. It’s just a better way forward for the project.”

Other changes include the departure of Battersea Power Station Development Company’s project director, Aidan McLeod, after just three years on the job. Since his departure Ian Feast, a project manager with experience at McAlpine, Hammerson and Cyril Sweett (as was), has been brought in, to be executive director of Phase 3. Again Tincknell insists there is no story to tell behind these changes, simply that “Aidan decided to leave of his own accord”.

Some of the speculation surrounding the project is that Battersea’s decision to push ahead with all of the first three phases concurrently has worsened the cost escalation, with one senior figure at a contractor saying it had created a “micro-climate” of enormous demand in one place. Tincknell admits keeping site workers has been very tough given buoyant conditions, citing the fact Carillion inducted on average 12 workers for every one of the 1,500 jobs on its phase because of the rate at which workers would be poached to work on other sites. But he rejects the idea of slowing things down. “If we did it one phase at a time we’d be here for 40 years. You’ve got to get on with it,” he says.

Good news

Balancing all this pain is the decision of Malaysian backers Sime Darby and SP Setia to remain completely committed to the project even though it has meant, Tincknell reveals, reaching into their pockets to inject additional equity. “The good news is that the shareholders are utterly committed to the regeneration of this building, despite its financial performance. This building […] is going to become an unbelievable centrepiece for this wider development. But it’s cost them.

“They are having to pay for this extra cost through large increases in the equity contribution they are making to the project. There aren’t many international investors and developers who would have done that.”

Meanwhile the project remains at the centre of a political firestorm following its decision to reduce the guaranteed proportion of affordable housing from 15% to 9% across the development (see “Affordable housing row”, above). While Wandsworth council has approved the deal, last week London’s Labour mayor Sadiq Khan accused the developer of “hoodwinking” the council, citing data from Wandsworth council stating Battersea is on course to make £1.8bn in profit - a figure the council says dates from 2008.

Tincknell maintains the affordable housing offer is actually far more generous than it is required to be under the terms of the National Planning Policy Framework, and points out that the regeneration is also underpinning the construction of the Northern line extension to Battersea and the creation of commercial space for 20,000 permanent jobs.

Hostile

But he says he is worried about what he sees as an increasingly hostile political climate for all developers in London. “We don’t want to end up becoming a political football, because that just knocks [the scheme]. All these benefits that we’re bringing on board, could become in jeopardy. We’re not another isolated, gated development.”

While the soaring construction costs have been the project’s biggest problem, Tincknell admits the fall in prime property sales has also had a “moderate, but impactful” effect on the plans.

So much so, he admits, there’s a chance that in Phase 4 to Phase 6 the development could be re-planned as a commercial rather than residential-led development. In addition, he says he has even scoped out the possibility of converting the second part of the Foster and Gehry Phase 3 to commercial. “The resi market is in a state of flux so we’ve looked at options regarding the buildings here [in the second part of Phase 3.] To make sure that we can make it happen we’ve looked at some different uses. That is just simply an exercise – it’s not some dramatic announcement,” he says, implying it is unlikely. “The reality is that actually we’ve done really well in sales of residential.” he says.

With the growing political controversy colliding with the construction woes, it is clear that whatever happens from now, the story of the regeneration of Battersea Power Station has got a long way to run yet.

Battersea’s phases

Construction has already begun on three of the Battersea project’s six phases.

Phase 1

Scheme: 865 homes, in two blocks designed by SimpsonHaugh and DRMM, sandwiched between the power station and overground line from Victoria
Cost: £400m
Contractor: Carillion, fixed-price lump sum, with Skanska delivering the fit-out

  • Carillion has completed construction of the first phase, which is currently being handed over to residents and commercial occupiers. While a change to the design of an energy centre led to a contract change after signing, Tincknell said rumours of problems and delays on this phase were incorrect and that Carillion had done a “brilliant job”, adding: “I’m certain they will be taking a further role in later phases.” Tincknell said he didn’t know if Carillion had made money on the contract, secured in the depths of the recession, and Carillion declined to answer whether the job has contributed to the £375m of losses on UK problem jobs it revealed last week.

Phase 2

Scheme: Redevelopment of the power station itself, designed by Wilkinson Eyre, to provide 253 flats
and 500,000ft2 of office space with a new energy centre beneath
Cost: More than £1.15bn
Contractor: Mace completed £100m of works rebuilding the towers, with Skanska delivering the rest

  • Originally estimated to cost £750m, Tincknell has not ruled out that this phase could double in cost, given the extent of problems. Set to contain the UK HQ for Apple, it will include leisure and other public uses and form the centrepiece of the scheme. Procured as a two stage, design-and-build contract, Skanska is undertaking works without the contract having been finalised, meaning the price is still unknown.

Phase 3

Scheme: Construction of 1,305 apartments in six blocks south of the power station, one designed by Norman Foster with five smaller ones by Frank Gehry
Cost: Unknown (estimated £1bn)
Construction manager: Sir Robert McAlpine

  • Work is at an early stage, with the original intention for Bouygues to carry out a £1bn design and build contract now scrapped, and McAlpine brought in as construction manager. Tincknell says Battersea is considering options to switch the later, southern portion of the scheme - which will be built over the new Battersea Northern line tube station – to commercial uses, but no decision has been taken. He says 60 apartments have been sold in the last nine months.

Affordable housing row

Wandsworth council last month approved Battersea’s request to reduce the guaranteed amount of affordable housing on the scheme by 250 homes to 386, equivalent to just 9% of the total. The change also saw the introduction of a clawback mechanism by which, if the development’s profitability - measured as Internal Rate of Return (IRR) - improves, the homes will be reinstated and even exceeded, up to a maximum of 33% of the total scheme.

However, viability consultant BNP Paribas Real Estate, working for the council, said that it was “very unlikely” anything other than the minimum level of affordable would be achieved, given that the IRR has fallen to 8.2%, well below the likely 15% threshold for reinstating.

London mayor Sadiq Khan said the change was “wholly unacceptable”, had “let Londoners down” and that he was seeking advice on how to stop it happening. Wandsworth’s planning committee chairman Richard Field said: “The escalating cost of restoring the power station building means this development project is facing significant challenges and the committee had a very difficult choice between accepting a potentially lower number of affordable homes, or refusing the application and risk[ing] losing all of them.”

Tincknell said: “Once the growth starts to come through, I’m optimistic we can see a good return of profit and IRR and we can start to look at reintroducing more affordable housing at that point.”