England’s tired further education colleges need about £5bn of work to bring them up to date. Simon Rawlinson of Davis Langdon explores the design, procurement and cost issues
01 Introduction
Further education (FE) colleges cater for post-school students of all ages, providing a range of general education and training. These include sixth-form education, vocational training and formal and informal community-based learning, as well as work-related training in partnership with local employers. FE colleges also serve the 14-16 age group, delivering education alongside local schools.
FE colleges are autonomous institutions in terms of the mix of syllabus they choose to teach, their sources of income and management of expenditure. The Learning and Skills Council (LSC) provides strategic support in terms of management, planning and funding to 384 FE colleges in England. Similar bodies support the sector in Scotland, Wales and Northern Ireland.
The LSC’s support naturally extends to the management and planning of the FE estate. This is a huge challenge, with significant issues of fitness for purpose and outstanding maintenance.
The poor condition of many FE colleges reflects a legacy of under-investment going back to the regime of polytechnics and technical colleges. Recent surveys of the FE estate in England have found that nearly half of the buildings require significant renewal and modernisation. The LSC estimates that this will cost about £5bn.
The objective of this ambitious programme, which has been earmarked for about £750m a year in government funding until 2011, is to create an FE estate that is fit for purpose, sustainable and efficient, and that aims to improve the recruitment, retention and performance of students and staff.
In a large number of cases, where a college’s estate is unfit for purpose, spread over multiple sites or in a particularly poor physical condition, the preferred strategy will be to consolidate the estate into a smaller number of purpose-built facilities, preferably on a single campus.
Investment in FE colleges can gain additional impetus where campus redevelopments are part of wider urban regeneration initiatives, and will sometimes provide the public sector anchor of the initial phase.
While this opportunity can lever access to land and funding, involvement in an urban regeneration scheme can have a wider impact on a college’s operation. It may affect funding and access to industry partners, short-term and long-term stakeholders, curriculum development and expectations of what the college should deliver.
Most FE colleges are infrequent construction clients, so the LSC is developing guidance on design quality, design assessment and sustainability; cost and performance benchmarking; and procurement based on contractor and consultant frameworks.
02 Development
An FE college’s property strategy defines the scope of all capital expenditure related to its estate. The strategy outlines the various property options to enable a college to meet the remit of its curriculum and identifies the best value options. The strategy is updated every three years.
An approved property strategy is a prerequisite for capital funding from the Learning and Skills Council (LSC) and will give the project team a clear brief as to the scope of the project and the client’s requirements.
The options available to deliver the college’s property strategy are influenced by a series of factors. These include:
- The condition of the estate, the location of facilities and their ability to meet the needs of staff, students and industry partners
- Current and forecast development of the curriculum, such as facilities for new subject areas with specialist requirements
- Current and forecast opportunities for linking up with local employers to provide work-related training
- Constraints related to the physical estate, such as plot size, that might affect refurbishment or redevelopment options
- The availability of surplus land that might provide opportunities for disposal and consolidation
- The effects of disruption to college activity caused by the implementation of each option
- Sources of extra funding available beyond that provided by the LSC.
Where the college is part of an urban regeneration masterplan, other factors to consider in the property strategy include:
- Co-ordination with other public sector partners to provide co-investment
- Responding to the needs of business and the local community in terms of extra facilities that the college estate could provide
- Meeting the area’s aspirations as stated in the local authority development plan.
03 Funding
When a college undertakes a development, it has a particularly close working relationship with the public sector funder.
In England, the college will consult the Learning and Skills Council’s (LSC) local partnership team, its regional provider financial management team and its regional property adviser on the project’s key education, finance and property dimensions.
In terms of funding, consultation will mean considering the options for borrowing from the private sector, the potential for a PPP or PFI, joint ventures and so on. Capital funding provided by he LSC will cover the public sector contribution to the following heads of cost:
- Construction costs
- Loose furniture, fixtures and equipment, IT and so on
- Professional fees
- VAT.
Additional allowances are made in the construction budget for investment in sustainability features, as well as for the usual site-related expenditure on abnormals.
In setting the level of capital grant, the LSC’s objective is to provide enough money to deliver a project that meets its quality, durability, fitness for purpose and affordability criteria. While additional funds are available to promote significantly better-quality design and more durable construction, budgets continue to be focused on delivering long-term value for money.
In order to proceed to detailed design and construction, the college must submit a funding application to the LSC. According to council procedures, funding approval is given at two levels. Below a £10m threshold, approval in principle is required. This requires that the project has been developed to about Stage C of the RIBA plan of work. For projects worth more than £10m, there is a further stage of approval in detail, based on criteria including design development beyond RIBA Stage D, receipt of planning permission, tendered construction costs and satisfactory completion of a financial appraisal of PPP and PFI options.
Public funding available to colleges for the main capital expenditure can range from 35% to 80%, depending on the circumstances of the scheme, its educational priority and the financial health of the institution. Colleges need to generate matched funding from a number of sources. These can include:
- Land disposal, although this requires LSC consent where the total value exceeds £1m or 5% of the college’s annual revenue. Some colleges based in urban locations have sold valuable sites to fund high-quality consolidation projects.
- Regional development agencies and other public bodies. By careful alignment of their relocation proposals with an agency’s economic and education priorities, colleges may be able to access additional public funding.
- Commercial loans, although the LSC must assess and approve these on the basis of the college’s ability to afford repayments.
- Third-party capital funding through a PPP or PFI. These could be based on a unitary charge mechanism or on some form of capital transfer of assets as part of a larger development scheme.
The council’s requirement for a reasonable degree of design and cost definition ahead of detailed approval helps to enforce a high degree of project discipline on the client and project team. This serves a number of purposes:
- Helping to ensure that all key design issues have been resolved and signed off ahead of procurement, particularly if the project is design and build.
- Enabling the college and its funders to assess the affordability of the proposal by examining firms’ construction costs, forecasts of running costs and finance costs, and any revenue that might be generated from third-party use of facilities.
- Helping to ensure that the new building responds to the funder’s design quality agenda.
04 Procurement and planning
Devising a procurement route to match the management capacity of the client body is a key issue. Typically, most of the management team will come from an education background and have little experience of the challenges of delivering such projects. It is important the project team is set up in such a way as to help the client body to carry out its role, without distracting it from the key business of managing the college.
As with all schemes, the selection of a procurement route should be carefully considered at the outset, taking into account the college’s requirements for project control, cost certainty and risk management, and aligning with the funding body’s approval requirements.
Given the disciplined funding regime, limited internal project management resources and requirements for absolute certainty of delivery to coincide with the academic calendar, design-and-build routes are commonly adopted on FE projects. Colleges can adopt alternative approaches so long as they can align with the funder’s approval processes, which require priced tenders in advance of final approval of funding.
For an FE college, the advantages of design and build are relatively early cost and programme certainty, with simplified project management and governance. The potential downsides of design and build are well known and the college needs to run a well managed system if it is to preserve its design intent, particularly if the contractor is appointed at a relatively early stage in the design programme.
Similarly, cost and programme certainty will depend on the college being able to manage its own internal stakeholders, keeping tight control on scope changes during both design development and construction.
A key aspect of procurement strategy is packaging a project to appeal to the current, active contractor market. Two-stage tendering, which limits contractor risk and arguably obtains contractor input on buildability, has become very common as fewer contractors have been prepared to bid competitively for projects on a single-stage basis. Early engagement with contractors in order to secure resources is also important.
In designing a two-stage competition, it is good practice to include the pricing of some high-value elements of the works, such as the substructure and frame, in the first stage, as well as preliminaries, overheads and profit. Furthermore, maintaining the client’s involvement in the second-stage bidding, possibly through the employer’s agent or client’s quantity surveyor, may help to encourage competitive pressure.
Given the complexity of managing the financial planning of an FE college development, the programme must take into account the full range of project activities. These can include:
- Providing sufficient time at the outset for designer and contractor input, together with decision-making by the client body
- Allowing time for consultation with third parties as required, and developing programme sequences that take into account known approval requirements and procedures
- Allowing sufficient time for the Official Journal of the European Union’s tendering procedures to be followed
- Establishing key academic dates in the programme including term times and examinations
- Fully planning all aspects of move management that might be necessary to meet opening dates, including furniture and fit-out works that might not be included within the scope of the construction contract.
05 Architecture
Expectations of the design quality of FE colleges have steadily grown and there is a body of completed projects that set challenging benchmarks for clients and designers alike.
In an education sector where the “client” is as likely to be a large-scale local employer as college staff or students, accommodation must meet quality standards informed by the private sector.
Buildings are increasingly required to communicate the range of activities taking place within a college and represent the institution as dynamic, modern and inclusive.
However, given the constrained nature of many of the sites on which FE colleges are located, the shape and form of the building will owe much to the plot aspect, shape and size, the context of the surrounding area and access.
Cabe’s recent report on the value of good design in education has added further impetus to the campaign to deliver high-quality college buildings.
The Learning and Skills Council (LSC) explicitly places importance on the procurement of good-quality buildings and focuses on the longevity and flexibility of the building fabric and the provision of good quality social and meeting space for students and staff. In recognition of this, the council can grant a further 10% of grant for high quality sustainable features tied to an aim to achieve a BREEAM “excellent” rating (see M&E design and sustainability, below).
The curriculum defines the overall spatial requirements, the size of the teaching spaces and the functional relationships that need to be accommodated.
However, teaching space is only one aspect of the mix. In order to ensure that colleges get the right balance of accommodation, the LSC has recently redefined the ideal allocation of floor area across four space types. It has added a new category of atrium space, which of course has a knock-on effect on building areas and costs.
The introduction of atriums helps the planning of assembly spaces, departmental adjacencies and circulation and support space, making the organisation of FE college buildings more logical and welcoming.
Within the space allocated for teaching and learning (see table, below), a wide range of subjects may need to be accommodated. Each subject type requires an allocation of floor area per student ranging from 1-2.5m2 for a lecture theatre or computer terminal to 7.5m2 for large-scale vocational subjects such as motor engineering workshops.
In addition to getting the key planning right, visual messages communicated by the building are also an important way of inspiring and motivating existing students and staff, as well as potential recruits.
Themes such as pride, openness or accessibility can be communicated by the general level of design and specification of the project, or by specific elements such as a feature entrance or atrium, which can act symbolically and literally as a “gateway to learning”.
The flexibility afforded by multi-functional spaces such as atriums is of the utmost importance for many FE institutions. They need to ensure that their building is future-proofed at a reasonable cost against changes in teaching methods, the curriculum and the organisation of the college itself.
These requirements should be captured in the brief, which should cover future modification. This includes vertical or horizontal expansion and the capability to reconfigure teaching space to accommodate organisational changes with minimal impact on the building fabric.
06 M&E design and sustainability
The drivers of M&E design in FE colleges are:
- Catering for current and future curriculum needs. This may require specialist systems to provide environmental control for vocational disciplines such as catering or dental nursing.
- Flexibility in the main plant configuration and the design of the distribution network, to accommodate changes arising from departmental changes or new teaching methods.
- Sufficient capacity to support planned increases in student density due to rising demand for certain subjects.
- Incorporation of specialist services, such as installations for catering and so on.
- Design of controls systems based on the principles of building “self-management” to avoid giving discretionary control over settings to users.
- Low, predictable running and maintenance costs based on static rather than active ventilation systems.
- Integrated electronic teaching facilities, such as smartboards, electronic timetabling and IT-intensive learning resource centres.
Sustainability has moved rapidly up the agenda and funding bodies are responding to the growing expectations of support for investment in green building features. In general, new FE college buildings are expected to achieve a minimum BREEAM rating of “very good” with an “excellent” rating being required to lever additional funding.
A recent study of college buildings examining the relation of quality, cost and design has underlined this trend by identifying aspects of building specification where expenditure should be focused to improve sustainability.
The building envelope is a good example, where improved insulation, solar performance and reduced air leakage can make a significant contribution to the reduction of building-related carbon emissions.
Where additional funding is being made available to improve sustainability performance, the LSC increasingly favours low-tech solutions – relying on building orientation, passive ventilation and thermal mass – rather than highly visible technology, such as wind turbines and photovoltaic cells, with long payback periods. Solar gain can also be mitigated through landscaping, which can contribute to the creation of a high-quality campus environment.
Other aspects of college design that can be adopted to emphasise an institute’s sustainability credentials, or to respond to the higher priority of the sustainability agenda, include altering the external facade material from aluminium to timber and using green roofs.
07 Cost breakdown
The cost breakdown is based on a four-storey college building with space arranged around an atrium.
The scheme has a number of sustainability features including displacement ventilation, a high-performance external envelope and a green roof.
The building is specified to be highly robust and the rates for partitions, doors, finishes and building services reflect this.
The rates are based on a design-and-build contract, procured via a two-stage tender. Rates are current in 2nd quarter 2007 for a south-east location.
The specification and rates in this model reflect a high-quality scheme that addresses the Learning and Skills Council’s (LSC) design-led agenda. The variation in cost between schemes can be wide because of the college’s discretion with regard to design standards in response to location, affordability and so on. Costs for the scope of work described in this model can range from about £1,700/m2 to more than £2,200/m2.
However, the following items excluded from the breakdown must be included in the submission to the LSC:
- Demolition and site preparation
- External works and services
- Loose furniture, fittings and operating equipment
- Decant costs
- Professional fees and VAT. These will typically increase the cost to more than £3,000/m2.