Jacqueline Backhaus and Henry Fitch A recent case involving a planning row at an east London faith centre is a reminder of the difficulty of overturning section 106 agreements through the courts
The Court of Appeal has issued a decision reinforcing the position that parties will, in the absence of exceptional circumstances, be held to the commitments they have made in a planning obligation (a bilateral section 106 agreement or unilateral undertaking).
Section 106 obligations are a prominent piece of the development puzzle. Developers are required to enter into them to mitigate the impact of the proposed development so that it is “sustainable” in line with the government’s aim for the planning system. Obligations range from sustainability measures to payments for the provision of additional school places to the construction of large pieces of infrastructure such as roads. Developers are often forced to accept unreasonable demands of local authorities in order to secure a planning permission, and many take the view that they may be able to escape these obligations further down the line. However, case law is very clear that parties will be held to their bargains when they enter into such obligations.
The court ruled that ‘to refuse an injunction would defeat the whole purpose of entering into the obligation’
In the case of the London Borough of Newham vs Ali, Shaik and Mohammed, the appellants sought to overturn an injunction granted to the council by the High Court to enforce the terms of a section 106 unilateral undertaking. The appellants were trustees of a charity that established a faith centre in east London without the benefit of planning permission and against which the council served an enforcement notice. On appeal, the secretary of state granted a temporary two-year planning permission on the basis of a section 106 unilateral undertaking in which the appellants covenanted to submit a planning application for a mixed-use scheme on the site within a year, failing which they would remove the faith centre.
No such application was submitted, so the council commenced court proceedings to enforce the terms of the undertaking. Parallel to the enforcement of the section 106 undertaking, a planning enforcement notice was served. The appellants appealed against this and against the council’s refusal of an application for planning permission for a faith centre on the site. The appeals were to be heard in June 2014, as this article went to press, six weeks after the date of the Court of Appeal hearing.
The Court of Appeal issued a decision robustly backing existing case law. It was held that:
- “Planning obligations entered into under section 106 of the 1990 Act are contractual obligations”
- The purpose of the power to grant an injunction for breach of a planning obligation “is to enforce an undertaking voluntarily given to a local planning authority”
- “Unless the local planning authority has been guilty of delay or unconscionable conduct … the court will usually exercise its discretion to grant an injunction in a case of substantial breach of a planning obligation”
- “The court is doing no more than holding the party in breach to its bargain”
- And, in this instance, “to refuse an injunction would defeat the whole purpose of entering into the section 106 obligation”.
While the court decided to suspend the injunction pending the outcome of the upcoming appeals, it noted that the power to suspend “should be exercised sparingly”.
This case highlights the importance of getting section 106 obligations right. The statutory right to apply for an amendment to a section 106 obligation only arises five years after the obligation was entered into, and even then it must be shown that it no longer serves a useful purpose - a difficult test to meet. Until that right arises, it is within the council’s discretion as to whether to enforce the terms of the obligation or to agree variations. If it does seek to enforce, a court will not investigate the planning merits of the obligation. If the breach is severe and there is no evidence of serious misconduct on the part of the council, the obligation will be enforced by the grant of an injunction.
Before entering into section 106 obligations, therefore, developers and land owners should:
- Understand the precise nature of the obligations they are committing to, and the consequences of breach
- Seek to negotiate with councils as far as possible and, in doing so, be aware of the statutory tests which planning obligations must meet
- Consider the option of submitting a unilateral undertaking on terms it finds acceptable and appealing against any refusal of planning permission on the grounds that the council considers the section 106 obligations deficient
- And ensure that the agreement itself is drafted so that their position is protected as far as possible and future developments are not prejudiced.
Jacqueline Backhaus is head of planning, and Henry Fitch a solicitor in the commercial property department at Trowers & Hamlins
No comments yet