The defendant engaged the claimant builder to carry out work at his home in Beaulieu. Work carried out was in excess of £500,000. Initial letter of intent provided for a limited amount of work to be carried out. However, that letter of intent said that the work would be carried out under the terms and conditions of the JCT 1998 Private Without Quantities Contract. The defendant sacked his construction advisers, and then proceeded to carry out some of the valuations on his own, before deciding to pay nothing further to the contractor.


The judge found that by signing and returning a letter of intent a contract had been formed. More importantly, the express contractual provisions had been included within the contract. This was because the letter, forming the contract, referred to a JCT contract, and article 5 of that contract provided for adjudication. The residential exception in the Construction Act did not apply, because the parties had agreed by contract to refer disputes to adjudication. The basis of the reference to adjudication was simply the contract to the parties and not the Construction Act.

The Issue

The contractor commenced an adjudication, and the adjudicator awarded £50,401.35. The defendant refused to pay on the basis that:

  • There was no written contract;
  • If there was a contract it had been terminated;
  • It was a dwelling which was excluded from the Housing Grants, Construction and Regeneration Act 1996; and
  • The agreement was contrary to the Unfair Terms in the Consumer contract Regulations 1999.