The board will feed power for the laboratory equipment, analytical equipment and fans in a 280 m2 area split over two floors. It is configured for a 250 A, three-phase incomer, metering and outgoing four 100 A, three-phase, plus single, 60 A and 10 A sub-mains.
The alternative market products available would mean using two boards, an mcb and a larger mccb. Completion of the installation from order took under three days, with a day’s labour saved compared to building and installing a standard mccb panel board. Time was saved as building the board only requires simple clipping in of mcbs.
Source
Electrical and Mechanical Contractor