We’ve been wowed by their scale, we’ve been wowed by their complexity and we’ve marvelled at the skill and dedication of the construction professionals behind them. Rory Olcayto and Kristina Smith take a look at projects that are simply...
The airport
Appropriately for a project the industry has fallen in love with, CM visited Heathrow’s Terminal 5 on Valentines Day, negotiating passport control and a maze-like access route in a quest to find Phil Wilbraham, BAA’s head of design, development, engineering and infrastructure on the project’s Leadership Team. We caught up with him in a busy site canteen and found that much like the signs dotted around the site that proclaim ‘One day you’ll be proud to say, I built T5’, Wilbraham is evangelical about the project. ‘Without doubt this project has raised the bar in the appreciation of construction,’ he says.
He’s not joking: the scale of T5 – a £4.3bn project to build a new terminal (T5A) and satellite (T5B) that will increase passenger numbers by 30 million – is mind boggling. It takes in a tube line extension, new train stations, new mainline railway tunnels, diverted rivers, a spur for the M25, a multi-storey car park, a hotel, an 87-metre-high control tower – plus two huge terminal buildings. One of them, T5A, measures 396 metres long by 176 metres wide and 40 metres high, making it the largest single-span structure in the UK. ‘T5A is enormous – one big floorplate, with no columns,’ explains Wilbraham. ‘It’s an incredible space. Just as railway stations were symbolic of travel in the 19th century, so T5 will be in the 21st century.’ Wilbraham says raising the roof was a major achievement for his team, using a strand-jacking technique perfected offsite.
What is perhaps more unbelievable than the scale of this project is the fact that it is on time and on budget. Wilbraham explains this is down to the integrated team approach that flows from the T5 Agreement, a unique contract that binds BAA closely to its key suppliers and means the airport operator carries all the risk. ‘At T5 it’s not about, “you do this, I do that”. There’s more trust. Everyone buys into team targets and the delivery of the project rather than just their own programmes,’ says Wilbraham.
Construction started in September 2002 and is on track to be completed this autumn. There will then follow a six-month period of trials and tests to ensure operational readiness for a 2008 opening. Another smaller development phase will wind up in 2010 when a second satellite building (T5C) is completed.
T5 is actually a collection of projects that Wilbraham says run in sequence and parallel. ‘We go through a fixed process of gateways. We get to a point called D-Day where design is complete, it’s been effectively priced and we know how long it will take to build. It’d be great to have one big D-Day for T5 but because of the scale and complexity, it’s just not possible.’
Wilbraham is now concerned with accommodating the retail teams and British Airways, which are looking to start their fit-out programmes as the shell and core are ready for handover.
It’s also worth mentioning that the T5 team has hit the million man hours without a reportable accident target on six occasions and previous safety records were broken last July when two million man hours were clocked up. Wilbraham expects that to continue, even though the delivery team will be running flat out as it approaches the finishing line. “Over the next nine months, there’s going to be much stretching of sinews,” he says. “But it’s been a joy to work on what is one of the UK’s greatest ever construction projects.”
The tower
The Burj Dubai is a statement. The world’s tallest building says prestige and power. And it’s not just the building which makes that statement: the engineering, resources and logistics employed to create the tower are awe-inspiring.
‘The design and construction methods and techniques we are using to create the tower are pushing the envelope as to what is practical with existing technologies,’ says Greg Sang, assistant director, projects, for developer Emaar Properties.
The tower, designed by architect Skidmore Owings & Merrill, will be more than 800 metres high and it reached its 100th storey in January. And to fox rival developers its eventual height remains a closely guarded secret.
Sang explains that the build is fast-track, so design continues as construction proceeds. ‘Our designers are located worldwide and without the internet, the huge amount of co-ordination and the finalisation of design details, at the speed required, it would not be possible.’
The concrete is delivered by the largest concrete pumps in the world and must remain pumpable while retaining the high early strength required for the three-day cycle of the jump form. The mix is a blend of Portland cement with silica fume, fly ash, and ground granulated slag.
The logistics, which will include moving 5,000 men at the peak, are aided by specially modified tower cranes and hoists which move at 100m a minute with a 3,200kg capacity. A specially developed GPS monitoring system ensures the tower’s accuracy.
South Korean contractor Samsung Corporation is still on track to complete it by the end of 2008. The development will also include a huge shopping mall and acres of water features.
“We are all fortunate be to able to participate in this historic project, but often we are so caught up in the business of doing what we are trained to do, we can forget to stand back and reflect on what is being achieved,’ says Sang.
The power plant
‘I’m driving down a dark highway,’ says Timo Kallio when CM tracks him down on his mobile phone. He’s heading home after another long day on the site of Olkiluoto 3, the half-built nuclear rector on Finland’s west coast, commissioned by his employer, power generation company Teollisuuden Voima Oy (TVO). When he adds that the project is now 18 months behind schedule, his journey home seems like an apt metaphor for the senior construction manager’s task ahead.
But this isn’t a project you would choose to rush – there can be no corners cut here. On completion in 2010/11 it will be Europe’s first nuclear power station in a decade and, more important, its first Pressurised Water Reactor – a third generation design that will be both more economic and, crucially, safer.
Despite the setbacks – blamed on bureaucracy and detailed design coordination – Kallio says his team is making good progress on the terror-proof, double-shell concrete wall of the reactor, which is designed to withstand the impact of an aeroplane. ‘In the past week, we’ve poured 4,000m3 to form the walls’ foundations,’ explains Kallio. It will need a whole lot more, as each is around 1.6m thick and will rise to a height of around 60 metres.
However, the next milestone will be the completion the turbine building cast and, once again, it’s a big operation. ‘It’ll require a pour of around 4500m3 – reinforcements are six metres thick,’ says Kallio.
It should be completed by May.
Kallio describes the Finnish health and safety regime in general as exacting, while at Okiluoto 3 it’s one of ‘zero tolerance’. But he says the foreign firms within the construction consortium – France’s Areva (now part of Bouygues) and Germany’s AG Seimens – have both welcomed the procedures and work well within its parameters.
‘We have less accidents here, than in other parts of the construction sector,’ claims Kallio, who adds that last month, work was halted on site for 48 hours when a routine inspection revealed small cracks in the base of a crane (one of 17 on site) It was dismantled and access restrictions were removed.
With years of experience in reactor builds behind him, Kallio is preparing for a big push as he attempts to get the project’s schedule back on track. It means, he says, making a crucial sacrifice: ‘We’ve had so many visitors – scientists and tourists – but it’s no longer safe and it takes up too much time. So no more site visits!’
The tunnel
Istanbul’s grand constructions and huge urban projects have come to define its history. Robust viaducts and immense city walls tell their own stories about the times in which they were built, while elegantly domed mosques and kilometre-long suspension bridges relate equally compelling narratives.
But in terms of sheer ambition, a new development – the Marmaray project – is set to trump them all. The multi-billion dollar rail infrastructure scheme will link Europe and Asia with an immersed tunnel, which at 58 metres will be the deepest in the world. Other aspects of the project involve 11km of bored tunnels cut trough solid rock to create a rail transport network aimed at easing the city’s nightmarish congestion problems.
The first section of the 1.4km tunnel is being placed in a precut trench in the Bosphorus, the busy waterway notorious for its unpredictable currents and frequent tectonic activity. With an earthquake of magnitude 7.5 on the Richter Scale predicted to hit the ancient city sometime in the next decade, the Marmaray tunnel has been designed to absorb it. One other aspect impacts upon every move the construction team makes: a rich seam of urban archaeology reaching back through seven millennia runs through the site.
A transcontinental tunnel was first considered in 1860 under the rule of the Ottoman Sultan Abdülmecid I. The idea was revisited over a century later when the Turkish government commissioned a feasibility study for a mass transit railway connection that would involve tunnelling under the water’s bed. The conclusion was positive, and in 2002, Avrasya Consult, a Turkish-Japanese joint venture in association with infrastructure expert Parsons Brinckerhoff (PB), won the contract for the design, tender, preparation, and construction supervision of the first railway crossing beneath the Bosphorus Straits.
Walter Grantz of PB, Marmaray’s immersed tube tunnel construction supervisor, was involved in the original feasibility study in 1985. ‘Then, as now, my focus was on the immersed tunnel and its alignment is same as the sketch I did on an A3 bit of paper 20 years ago!’ he says.
Grantz (pictured below) explains that the tunnel consists of 11 elements, each one 135 metres long and weighing 18,000 tonnes. ‘We build the steel-reinforced concrete box sections in dry docks 40km away in the Sea of Marmara,’ he says. A bid to secure space at the city’s busy shipyards failed. It has meant dealing with strange water currents when the elements are floated to site. An upper flow of fresh water heads south from the Black Sea, meeting a counter-current beneath of salt water heading north from the Sea of Marmara. ‘They range up to six knots at the surface and when you consider that 50,000 major ships use the straits every year, it makes placing the elements in the trench a very challenging proposition.’
Grantz’s colleague, project manager Daniel Horgan, has been on site for the past two-and-a-half years and has found other distractions. ‘The city has such a rich history that you can find something new for every few metres you dig,’ he says, recalling the spectacular uncovering of the ancient sea port of Theodosius. It was found in 2005 when clearing a site for one of Marmaray’s railway stations on the Asian side of Istanbul. Eight sunken ships were unearthed as well as the stone remains of the harbour itself along with 4th century bric-a-brac such as leather sandals and hair brushes. Grantz’s immersed tunnel team, meanwhile, was isolated from archaeological findings – although they did find one pot. ‘We thought for a while that we might have to dredge the Bosphorus with a spoon!’ he says with a chuckle.
A more pressing concern for the waterborne team is ensuring the tunnel copes with earthquake activity, which is sadly a certainty in this geologically volatile region. Immersion within the seabed is part of the solution but the weak point is the joint between the two tunnel types, where the underwater section joins with the rock-bored sections of the link. Flexible, thick rubber rings reinforced by steel plates will act like gaskets in the event of a tremor, allowing sections either side of the joint to move.
‘Touch wood there’s been no tremors so far,’ says Grantz, adding that the ground conditions are important too. ‘Liquefaction can occur on the sandy bed during tremors so we’ve extended the tunnel foundation 16 metres below the bed and stabilised nine metres of soil below that with mortar.’
An Irishmen himself, Horgan highlights the international nature of the project where the challenge is integrating the various different work cultures: Turkish, Japanese, British and American. ‘It can be frustrating at times and requires extra and careful communication. But working in a multi-cultural environment on a project that links two continents, well, we’re making history here.’
The swimming pool
A swimming pool clad inside and out in bubble-wrap around a steel structure based on the complex pattern of soap bubbles. Now surely only an architect could come up with something like that?
Not so in the case of the National Swimming Centre in Beijing, currently under construction for the 2008 Olympics. Known as the Cube, the building is the result of a unique collaboration between PTW Architects, structural engineer Arup and contractor China State Construction Engineering Corporation who won an international competition to design and build the centre.
‘It was a highly unusual way of working,’ says Tristram Carfrae, director of Arup. ‘We sat down at the first meeting and said what we thought a swimming centre should be like from an engineering point of view.’
The engineers came up with an insulated greenhouse to aid the year-round heating required and provide natural light. ETFE, acoustically transparent, would be a good alternative to glass which only adds to the noise reflecting from tiles and water.
The architects thought otherwise. ‘All our ideas were ignored at first,’ says Carfrae. ‘For four weeks they explored lots of different shapes and philosophies. The Chinese and Australian teams were looking in different directions. Then, in a period of weeks, everything came together.’
The catalysing moment was the discovery that Herzog de Meuron’s bird’s nest was to be the pool’s neighbour. ‘It’s probably just how I remember it. But we said “their’s is red and round so we will have a square blue one”. Everybody agreed.’
With only the structure of the steelwork to be resolved, Arup came up with an unique solution after an internet search. The structure, based on a mathematical theory developed in 1993 by professors Weaire and Phelan, would mimic the pattern formed by soap bubbles squashed together.
The design of the steel, formed in tubular sections, was a mammoth task, requiring new software to model it. Arup fully designed the package before it was handed over to the contractor and for the first time Arup handed over the model in both 3D and 2D.
Arup proposed welding the nodes where the tubes meet in the factory with joints mid-length in the tubes done on site. But the Chinese contractor elected to do the welding in situ, due to the availability of labour and scaffold. ‘In their economy and their situation, it was the cheapest most effective way to do it,’ explains Carfrae.
To date the steelwork is up and the external cladding complete. Inside, work on the cladding is still ongoing and the pool should be complete by the end of 2007.
Everything has been sourced from China, except the ETFE which comes from British firm Vector Foiltec. Unusally the cladding contract, shared with a local firm, includes the maintenance and operation of the cladding since it must be pumped to maintain its cushion-like form.
‘From the outside it looks fantastic,’ says Carfrae. ‘I can’t wait to see what it looks like from the inside.’
A project on a grand scale
The Marmaray project is a new and upgraded railway that will be 76km long and is scheduled for completion in 2011.
The main structures and systems include: the immersed tube tunnel (1.4 km), bored tunnels (9.8 km), cut and cover tunnels (2.4 km), three new underground stations, 37 new or upgraded surface stations, operations control centre, yards, workshops, maintenance facilities, 250km of new track, electrical and mechanical systems including tunnel ventilation, rolling stock, signaling and a 25kV electrification system. The railway will support huge trains that can carry 3,500 passengers, intercity trains and freight that could travel from Inverness to Baghdad.
Tomorrow’s people
Tristram Carfrae has already been recognised for his outstanding engineering achievements. In November last year he was made a Royal Designer for Industry, the highest accolade that a UK designer can receive.
He is one of Tomorrow’s People because the ideas and tools he is developing today will influence the way that structural engineering develops. For example, the 3D documentation, used for the first time on the Beijing National Swimming Centre project, is now being used on other Arup jobs around the globe.
Carfrae’s team is now employing that technology to build a retrospective model of Sydney Opera house which will combine information from 26 different databases with the geometric data. ‘This way of doing things is going to be a huge change in the next 10 years, although at this point it’s difficult to forecast where the benefits will come from,’ says Carfrae.
Based in Sydney, Australia, since 1990, Carfrae has been a design leader on high-profile jobs such as the Manchester City Stadium as well as the Beijing project. He also heads up an Arup group responsible for promoting innovation, design and technical excellence throughout the firm and is a director on the Arup Group main board.
Source
Construction Manager
No comments yet