Welcome to building.co.uk. This site uses cookies. Read our policy.

 £/system
X-ray MVTHR scanner200,000
CT examiner600,000
Network interface50,000
X-ray scanner (hand baggage)70,000
Tilt tray sorter complete10,000/m
Make-up carousel75,000
Reclaim carousel90,000
All costs are net of builders’ work, preliminaries and professional fees.
 ££/m2 GIFA%
Substructure4,307,000172.286.02
Undercroft construction; reduced-level excavation, 200mm-thick reinforced concrete ground slab, hardcore, damp-proof membrane: 8,550m2 @ £300   
Ground slab; 200mm-thick reinforced insitu concrete bed, hardcore, damp-proof membrane: 1,050m2 @ £120   
Extra for retaining walls, linings etc: item @ £320,000   
Extra for foundations; isolated pad and raft foundations: 9,600m2 @ £105   
Allowance for below-ground drainage and incoming services: 9,600m2 @ £30   
Frame3,585,800143.435.01
Allowance for structural steel framing based on 80kg/m2 (average rate for universal and hollow sections): 1,330t @ £2,300   
Allowance for structural steelwork to office mezzanine, based on 35kg/m2: 25t @ £1,950   
Allowance for additional framing/trimming to service risers and openings for baggage conveyors: item @ £160,000   
Cold-rolled galvanised steel roof purlins; 1.6m centres, 4.5kg/m average weight: 9,300m @ £10   
Intumescent 1hr fire-resistant paint finish: 15,000m2 @ £15   
Upper floors1,570,00062.802.20
Prestressed, precast concrete structural suspended floor units; 50mm-thick structural topping: 14,800m2 @ £95   
Extra for 7.5kN/m2 floor loading to plant room areas: 500m2 @ £8   
Extra for formation of openings, lift and escalator pits etc: item @ £160,000   
Roof5,551,500222.067.76
Roof cladding, including perforated feature cladding, raised-seam aluminium roofing, structural deck, insulation, vapour barrier and liner: 9,200m2 @ £285   
Extra for rooflights, with sealed double-glazed units, powder-coated aluminium framing and secondary steelwork including perforated panel sunscreens: 900m2 @ £950   
Allowance for work to boundaries, gutters, rooflights, openings etc: 7,500m @ £80   
Precast concrete roof slabs; 7.5kN/m2 floor loading, for roof-level plant, with waterproof membrane, plinths and bases: 450m2 @ £250   
Full-length entrance/set-down canopy, complete with hollow-section framing, curved aluminium raised-seam roofing, rooflights: 1,300m2 @ £900   
Allowance for roof safety system: 1,200m @ £160   
Stairs807,00032.281.13
Steel feature stair and half-landings, overall rise 5.50m, with toughened, laminated glass balustrade, stainless steel handrails, finishes: 2 nr @ £40,000   
Steel feature stair, overall rise 3.00m, with toughened, laminated glass balustrade, stainless steel handrails, finishes: 2 nr @ £32,000   
Precast concrete stairs and half-landings, overall rise 5.50m, with stainless steel handrails, finishes: 2 nr @ £26,000   
Precast concrete stairs and half-landings, overall rise 5.50m, with polyester powder-coated steel handrails, finishes: 16 nr @ £20,000   
Balustrade and handrail to mezzanine and first floor with toughened laminated glass balustrade and stainless steel handrail: 190m @ £900   
Allowance for access platforms and stairs to plant rooms: item @ £100,000   
Allowance for roof access, stairs and hatches: item @ £20,000   
External walls, windows and doors6,840,200273.619.57
Wall cladding; aluminium-faced composite panels with 25% glazing in aluminium-framed sealed double-glazed units, flashings and accessories: internal lining, including 140mm-thick blockwork backing wall: 7,000m2 @ £650   
Curtain walling; silicone-sealed double-glazed units, colour-coated aluminium framing, flashings and accessories: 1,750m2 @ £900   
Extra for shopfront feature curtain walling to entrance areas: 100m2 @ £400   
Extra for triple-glazing and increased depth of framing to airside curtain walling: 480m2 @ £240   
Louvre panels to plant areas, of powder-coated aluminium: 250m2 @ £400   
Principal entrance double doorsets (2 nr) and wind lobby, fully glazed with ironmongery and accessories: 6 nr @ £50,000   
Aluminium-faced powder-coated vision-panel double doors and frames, with ironmongery: 10 nr @ £10,000   
High-speed sectional doors to baggage handling, electrically operated, including controls: 4 nr @ £15,000   
Internal walls and partitions2,099,00083.962.94
Insitu concrete shear walls to stair cores and service risers, 250mm average thickness: 2,500m2 @ £140   
Blockwork partitions, 140mm average thickness, with head restraint: 7,700m2 @ £60   
Metal stud partitions; 5.0m high, single-layer impact-resistant board, single-layer wallboard, each side, to public areas: 2,500m2 @ £80   
Metal stud partitions; double-layer wallboard, each side, to office areas: 1,050m2 @ £60   
Metal stud partitions; shaftwall construction, double-layer fireline board, single-layer core board, one side only: 2,000m2 @ £100   
Fascia panel to ticket sales desks: 40m @ £800   
Fully glazed shopfronts; fascia panel: 160m @ £3,200   
Toilet cubicle partitions: 50 nr @ £1,600   
Melamine-faced solid-laminate access panelling to WCs etc: 150 nr @ £800   
Allowance for additional screens and partitions: item @ £80,000   
Internal doors371,10014.840.52
Flush doors to public areas, solid-core laminate/veneer-faced with hardwood frames and ironmongery: 100 nr @ £1,450   
Flush doors to administration areas, solid-core laminate/veneer-faced with hardwood frames and ironmongery: 72 nr @ £1,300   
Duct access doors: 100 nr @ £1,125   
Allowance for additional services access panels: item @ £20,000   
Wall finishes1,224,60048.981.71
Independent wall lining; plasterboard lining to inner face of external walls: 4,600m2 @ £50   
Extra over plasterboard linings for laminate-finish wall panelling: 2,500m2 @ £15   
Laminate-finish wall panelling to blockwork: 3,700m2 @ £65   
Ceramic tiles with sand cement backing to concrete or blockwork: 300m2 @ £65   
13mm double-coat lightweight plaster and two coats emulsion paint to blockwork/concrete: 10,900m2 @ £20   
Two coats emulsion paint to blockwork: 6,650m2 @ £5   
Skim coat and two coats emulsion paint to plasterboard: 5,900m2 @ £12   
Wall protectors, stainless steel protective rails: 1,500m @ £250   
Floor finishes1,720,50068.822.41
Sand cement screed, average 40mm thick: 10,040m2 @ £24   
Granite terrazzo floor tiles, 300 x 300mm, including allowance for skirtings, movement joints and brass division strips: 6,540m2 @ £130   
Vitrified ceramic tiles, 400 x 400mm, including allowance for skirtings and movement joints: 1,100m2 @ £95   
Raised access floor, carpet tile, to office areas: 800m2 @ £65   
Heavy-duty carpet tiles, including allowance for skirtings: 2,400m2 @ £45   
Vinyl floor tiles and levelling screed, including allowance for skirtings, to core areas: 2,550m2 @ £40   
Extra for finish to WCs: 400m2 @ £76   
Concrete hardener to concession shells, plant rooms and baggage handling, and skirtings: 10,300m2 @ £8   
Allowance for additional floor finishes: item @ £100,000   
Suspended ceilings, including metal pan tiles and lay-in grid, to check-in, ticket sales and office areas: 1,650m2 @ £65   
Suspended ceilings, including mineral-fibre tiles and lay-in tiles, to core areas: 440m2 @ £40   
Extra over ceiling finishes generally for acoustic treatment to mall/queuing areas: 6,000m2 @ £35   
Extra for moisture-resistant ceiling tiles to WC areas: 400m2 @ £10   
Concrete sealant to concession shells, plant rooms and baggage handling: 10,300m2 @ £10   
Extra for 4hr fire protection to areas of undercroft plant room soffit: 500m2 @ £100   
Furniture and fittings1,770,00070.802.49
Check-in desks: 64 nr @ £5,000   
Out-of-gauge baggage counter: item @ £40,000   
Information and security desks: item @ £80,000   
Ticket desks: 20 nr @ £10,000   
Statutory and directional signage: item @ £240,000   
Seating to check-in and departure lounge areas: 400 nr @ £250   
Allowance for fixtures and fittings generally to public areas: item @ £320,000   
Allowance for furniture and equipment to check-in and ticket sales areas (excluding IT installations): item @ £320,000   
Allowance for fittings to back-of-house areas: item @ £150,000   
Sanitary fittings114,5004.580.16
WCs, urinals, hand basins generally: 150 nr @ £650   
Allowance for fittings for disabled WCs: item @ £8,100   
Cleaners’ sinks: 6 nr @ £650   
Allowance for drinking-water fountains: item @ £5,000   
Disposal installations445,00017.800.63
Rainwater disposal, including cast-iron downpipes and fittings: 25,000m2 @ £6   
Waste, soil and vent installation, including uPVC pipework and fittings: 25,000m2 @ £8   
Allowance for pumped disposal from undercroft: item @ £95,000   
Water installations450,00018.000.63
Hot and cold water service, including calorifiers, hot and cold water storage and distribution: 25,000m2 @ £18   
Space heating and air treatment9,610,900384.4413.52
Gas installation: item @ £32,000   
Low-temperature hot water heating (boiler plant), including stainless steel flues, pumps and valves, distribution within plant rooms, insulation: 25,000m2 @ £24    
Low-temperature hot water heating (perimeter heating), including LTHW elements and distribution: 25,000m2 @ £38   
Chilled water installation, including chillers and cooling towers (total load 2,500kW), pressurisation unit, pumps and valves, distribution pipework, insulation and trace heating: 25,000m2 @ £64   
Supply and extract ventilation: air-handling unit with heating and cooling batteries; ductwork in risers and plant rooms: 25,000m2 @ £32   
Supply and extract ventilation: displacement system; ductwork, grilles and diffusers, insulation; to public areas: 13,500m2 @ £290   
Air-conditioning: four-pipe fan-coil installation to office areas, check-in etc; LTHW and chilled water distribution, condensate drainage, fan-coil units, ductwork, insulation, grilles and diffusers: 1,650m2 @ £250   
Allowance for services to comms rooms: item @ £240,000   
Mechanical ventilation to baggage handling and plant rooms: 7,400m2 @ £80   
Toilet extract installation: 25,000m2 @ £8   
Allowance for smoke extract to public areas, roof-level extract: 13,500m2 @ £10   
Extra over mechanical ventilation for smoke extract to baggage handling: 4,200m2 @ £32   
Electrical installations6,913,800276.559.72
HV switchgear, 5mVA, transformers, HV cable, LV switchgear: item @ £1,600,000   
Standby generation (1,750kVA) for essential services only: item @ £800,000   
Mains and sub-mains installation: 25,000m2 @ £46   
Small power distribution: 25,000m2 @ £16   
Lighting and luminaires to public areas: 13,500m2 @ £120   
Lighting and luminaires to check-in, ticket sales and offices: 1,650m2 @ £90   
Lighting and luminaires to core, plant and baggage handling: 9,850m2 @ £65   
Emergency lighting installation: 25,000m2 @ £15   
Power to mechanical services: item @ £180,000   
Lift installations1,260,00050.401.77
26-person, 0.6m/s electro-hydraulic lift serving 2 floors: 2 nr @ £150,000   
2,000kg goods lift serving 3 floors: 2 nr @ £160,000   
Escalator, 0.5m/s, 1m step-width, 5.2m rise, glass balustrade: 4 nr @ £160,000   
Protective installations1,210,00048.401.70
Lightning protection: 25,000m2 @ £3   
Earthing and bonding: 25,000m2 @ £5   
Sprinkler installation, with storage tank, pumps and pipework: 25,000m2 @ £32   
Allowance for dry-riser and hose-reel installations: item @ £160,000   
Fire-suppression installation to comms room: item @ £50,000   
Communications installations4,075,000163.005.73
Fully addressable fire and smoke detection and alarm system: 25,000m2 @ £30   
Voice/public address system with interfaces to flight information, fire and security systems: 25,000m2 @ £16   
Intruder detection: 25,000m2 @ £10   
Allowance for security, CCTV and access control: 25,000m2 @ £32   
Wireways for telephones, data and structured cable: 25,000m2 @ £13   
Structured cable installation, linking check-in, ticket desks and security control points: 25,000m2 @ £30   
Allowance for flight information display system; 100 LED displays, 150 monitors: item @ £800,000   
Special installations1,350,00054.001.90
Building management system: 25,000m2 @ £54   
(Baggage-handling installation excluded)   
Builder’s work in connection760,00030.401.07%
Allowance for forming holes, chases etc @ 3%: item @ £760,000   
Preliminaries and contingencies13,915,200556.6119.57
Allowance for contractor’s overheads, site establishment and site supervision @ 18%: item @ £10,315,000   
Allowance for commissioning management: item @ £250,000   
Allowance for design reserve @ 5%: item @ £3,350,200   
Total construction cost (building only)71,100,0002844.00100.00
Acknowledgments: Davis Langdon would like to thank Richard Gammon of Capita Architecture and Tony Potter, Nigel Addy, John Grounds and David Unwin of Davis Langdon’s airports sector for their assistance in producing this cost model