Keep up to dateEngineering services: Costs | |
Sector | Cost £/m² |
Commercial offices | £435-750 |
Education | £325-525 |
Healthcare | £555-655 |
Residential | £350-960 |
Hotels | £535-750 |
Retail | £325-550 |
Lifts and escalators: Lead times | |
Components | Lead time |
Network components: switches, routers, chassis, wireless networks. | 0-2 weeks |
Bespoke network components such as specialised routers | 4-6 weeks |
Standard AV components: LCD Screens, LCD Projectors, sound reinforcement | 2-4 weeks |
Bespoke AV systems: control systems, lighting rigs and so on | 6-8 weeks |
Enterprise components: PCs, laptops, “thin clients”, standard servers | 2-4 weeks |
Bespoke enterprise components: specialised blade enclosures, server racks and so on | 6-8 weeks |