Keep up to dateChecking out – a post-completion analysis | ||
Location | Total cost (£) | Cost/functional area (£) |
Guest rooms | 5,938,224 | 286.57m2 |
Guest room corridors | 617,635 | 29.81m2 |
Roof works | 496,012 | 23.94m2 |
Fire Life Safety scope | 615,919 | 29.72m2 |
Ground floor | 575,722 | 27.78m2 |
Asbestos removal | 115,441 | 5.57m2 |
Hot and cold water & drainage | 1,941,308 | 93.68m2 |
Sprinklers | 854,389 | 41.23m2 |
Air conditioning and heating | 1,838,703 | 88.73m2 |
Supply and extract air | 1,664,552 | 80.33m2 |
Electrical | 1,949,753 | 94.09m2 |
Signage, external and internal | 191,486 | 9.24m2 |
Window replacement | 315,767 | 15.24m2 |
Arrival experience, lobby & façade | 449,859 | 21.71m2 |
Building management system | 516,786 | 24.94m2 |
Fire Life Safety work to garage | 803,980 | 38.80m2 |
Net construction cost: | 18,885,537 | 911.38m2 |
Preliminaries & site management | 2,272,509 | 109.67m2 |
Professional fees | 3,285,482 | 158.55m2 |
Final project cost | 24,443,528 | 1,179.6m2 |