Guideline areas for generic spaces
Room useCommentRoom size m²
WC for the disabled, pantry, cleaners’ room or disposal holding room 4.5-5
Counselling, staff or client interview, single person office, clean utility, dirty utility room, nurses’ weighing room 9-10
Examination/consultation, treatment room, single person therapy treatment space, small group/meeting room for four to six people, two-person office 13.5-15
Treatment room, group room for six to eight people, meeting room for eight to 10 people, office for three or four people. These rooms could be connected by folding acoustic screens, to be opened up for larger group or therapy activitiesSuch a space could also be sub-divided to form two 9-10 m² rooms 18-20
Allowance: circulation, subdivision, voids, service ducts etc  28-30%
Source: Planning and design guidance - primary and social care facilities. Dimensions of public spaces such as waiting rooms are defined in Health Building Note HBN 40 – Common Activity Spaces.
Primary healthcare centre cost breakdown
 element costcost/m² gfa £% of total cost
Substructure56,850.00111.478.97
    
Excavation and disposal140 m3 @ 30    
Strip foundation with cavity masonry wall 150 m @ 130    
150 mm thick ground floor slab with thickenings 510 m² @ 65    
    
Roof83,050.00162.8413.10
    
Precast concrete planks 510 m² @ 55    
Single ply membrane, including insulation and labours 510 m² @ 90    
Allowance for roof inlets Item @ 2,500    
Aluminium rainwater down pipes 30 m @ 60    
Sunpipes 8 @ 600    
    
External walls33,600.0065.885.30
    
Brick cavity wall, facing brick outer skin with cavity, insulation,    
140 mm inner blockwork leaf 240 m² @ 140    
    
Windows and external doors49,650.0097.357.83
    
Aluminium double-glazed windows 60 m² @ 350    
Single aluminium doors 3 @ 1,400    
Double aluminium framed glazed doors and screens to entrance 22 m² @ 500    
Single steel door to plant room Item @ 1,300    
Fixed metal grilles to windows Item @ 5,000    
Electrical roller shutter to glazed entrance screens, including controls 22 m² @ 325    
    
Internal walls18,400.0036.082.90
    
100 blockwork 470 m² @ 35    
Stud partition Item @ 450    
Security counter grille to reception desk Item @ 1,500    
    
Internal doors28,750.0056.374.53
    
Internal doors, wood veneer, stainless steel ironmongery 20 @ 900    
Internal doors and screen, inner door to lobby 5m²@ 500    
Wrot softwood storage cupboard door, stainless steel ironmongery 3 @ 450    
Fire-rated doors, stainless steel ironmongery 5 @ 1,100    
Double internal fire rated doors, stainless steel ironmongery Item @ 1,400    
    
Wall finishes16,800.0032.942.65
    
Plaster and one mist coat, three coats of emulsion paint 900 m² @ 15    
Ceramic wall tiles 60 m² @ 55    
    
Floor finishes23,850.0046.763.76
    
Screed 510m² @ 15    
Carpet tiles to reception area, staff areas 145 m² @ 25    
Vinyl to WC areas and practical areas, including skirtings 320 m² @ 30    
Heavy duty vinyl to entrance area, dirty areas 40 m² @ 40    
Entrance matting with aluminium matwell 5 m² @ 275    
    
Ceiling finishes 17,575 34.462.77
    
Mineral fibre suspended ceilings 80 m² @ 30    
Plasterboard ceiling, plaster skim and emulsion paint finish 405 m² @ 35    
Moisture resistance plasterboard ceiling, plaster skim and emulsion finish 25 m² @ 40    
    
Fittings and fixings 32,700 64.125.16
    
Supply and install group one medical equipment (fixed furniture)    
Fit only group two and three medical equipment (loose equipment)   
Reception area, desks and fixed furniture item @ 8,000    
Waiting room item @ 5,000    
Consulting rooms 6 @ 1,600    
Treatment rooms 2 @ 1,100    
Nurse rooms, including health visitor 4 @ 1,100    
Records store Item @ 500    
Admin rooms 2 @ 600    
Multipurpose/interview rooms 2 @ 900    
    
Sanitary fittings 14,280 28.002.25
    
WCs 6 @ 300    
Hand basins 6 @ 180    
Medical handwash basins 12 @ 500    
Disabled toilet, including WC, wash hand basin, grab rails and other fittings 2 @ 1,200    
Cleaners sink, 510 × 380 2 @ 700    
Baby changing unit Item @ 400    
Sink and slop hopper Item @ 1,200    
    
Disposal installations 4,080 8.000.64
    
Waste, soil and vent installation; PVCu pipework and fittings 510 m² @ 8.00    
    
Water installations 13,300 26.082.10
    
Cold water system 28 @ 250    
Hot water system 21 @ 300    
    
Space heating and air treatment 40,800 80.006.44
    
Space heating, all costs associated with the supply and installation of the heating system,    
temperature control and distribution pipework 510 m² @ 80    
    
Ventilation installations 19,500 38.243.08
    
Extract ventilation to clean areas Item @ 12,000    
Extract ventilation to dirty areas Item @ 5,000    
Extract ventilation to toilet areas Item @ 2,500    
    
Electrical installations 45,900 90.007.24
    
Mains and sub-mains installation 510 m² @ 20    
Small power installation 510 m² @ 30   
Lighting and general luminaires; emergency lighting 510 m² @ 40    
    
Gas installation 1,500 2.940.24
    
Lightning protection installation 2,000 3.920.32
    
Communications installation 25,400 49.804.01
    
Fire alarm installation; smoke detectors; call points 510 m² @ 15    
Telephone and data wireways; internal telephone system 510 m² @ 5    
Patient call and induction loop systems Item @ 5,000    
Security installation; intruder detection, panic buttons, disabled toilet alarm,    
CCTV 510 m² @ 20    
    
Building management system installation 5,000 9.800.79
    
Builder’s work in connection 4,500 8.820.71
    
Preliminaries and contingencies96,515189.2515.22
    
Preliminaries allow 15% Item 80,400   
Contingencies allow 3% Item 16,115   
    
Total construction cost – building only634,000.001,243.14100.00
    
Alternative specifications £/m² change based on gifa   
    
Option 1: Provide access door controls to single door 1.50   
Option 2: Automatic sliding door to entrance 45.00   
Option 3: Anti bacterial wipe-down paint to consulting, nurses and treatment rooms 12.00   
Option 4: Replace flat roof with pitched roof and concrete tiles –38.00   
Option 5: Replace facing brick cavity wall with rendered blockwork cavity wall –8.50   
Option 6: Enhanced security, roller shutters to windows 65.00   
Option 7: Sliding folding partition to divide large room 12.00   
Option 8: Replacing vinyl tiles with rubber tiles 15.00   
Option 9: Sound-absorbent walling to waiting room 10.50   
Option 10: Add shower for staff 6.50   
Location factors
Inner London1.09
Outer London1.03
South-west0.97
East Midlands0.93
West Midlands0.93
East Anglia0.97
Wales0.91
Yorkshire and Humberside0.95
North-west0.94
North0.94
Scotland0.92
Northern Ireland0.75