Welcome to building.co.uk. This site uses cookies. Read our policy.

Cost of shell-and-core construction
 element costcost/m² GFA £% of total cost
    
Substructure403,00066.618.06
    
Excavation, footings, column bases, filling to levels, ground slab 3100 m² @ 130   
    
Frame and upper floors661,500109.3413.23
    
Structural steelwork; UB and UC sections 300 t @ 1,400   
Composite slab, metal deck and insitu concrete 2900 m² @ 60   
Fire protection to steelwork item @ 50,000   
Allowance for miscellaneous works item @ 17,500    
    
Roof639,500105.712.79
    
Insitu concrete roof slab; metal deck and insitu concrete 3080 m² @ 60   
Insitu concrete rooflight upstand walls 120 m² @ 160    
Timber roof trusses item @ 60,000    
Monopitch roof, coated aluminium roof cladding, including purlins, trims, cappings, insulation 1780 m² @ 100    
Flat roof, asphalt, including insulation, trims, skirtings, flashings, linings to gutters, paving slabs 1500 m² @ 90    
Mansafe system item @ 12,500   
Rooflights 100 m² @ 500   
    
Stairs108,50017.932.17
    
Main steel internal staircases; handrails and balustrades (rate per flight) 4 @ 8,000   
Steel external staircases; handrails, balustrades, framing (rate per flight) 4nr @ 10,000   
Atrium balustrading 45 m @ 700   
Miscellaneous metalwork in shafts and risers Item @ 5,000   
    
External walls, windows and doors820,200135.5716.4
    
Coated aluminium double glazed curtain walling 150 m² @ 375   
Extra for fire escape doors 8 @ 1,000   
Coated aluminium double glazed window system 850 m² @ 350    
Solar shading; fixed aluminium louvres 300 m @ 300   
Glazed main double entrance doors @ 6,000   
Aluminium wall cladding to roof level plant etc. 610 m² @ 45   
Render on blockwork, insulation and boarding 550 m² @ 160   
Facing brickwork in cavity walls 690 m² @ 150    
Facing brick cladding to columns 675 m² @ 100    
Miscellaneous masonry item @ 70,000   
    
Internal walls and partitions219,20036.234.38
    
Blockwork 1200 m² @ 50   
Drywall partition; 1 hour FR 570 m² @ 60    
Hardwood glazed screens; 1 hour FR 180 m² @ 500    
WC cubicles Item @ 35,000   
    
Internal doors 98,00016.21.96
    
Hardwood doors and frames; stainless steel ironmongery 80 @ 1,100   
Allowance for fire containment in common areas item @ 10,000   
    
Wall finishes66,40010.981.33
    
Emulsion paint to wall surfaces generally item @ 40,000   
Plasterboard to cores and common areas 1650 m² @ 16   
    
Floor finishes 75,20012.431.5
    
Screeds to cores and common areas; 150 thick to make up levels 640 m² @ 20    
Carpet tiling to common areas 170 m² @ 30   
Ceramic tiling to cores and common areas 470 m² @ 90    
Floor finishes to internal stairs Item @ 5,000   
Entrance matting 2 @ 5,000   
    
Ceiling finishes52,5008.681.05
    
Plasterboard ceiling and bulkheads; to core and common areas 1050 m² @ 50    
    
Furniture and fittings38,0006.280.76
    
Granite vanitary units item @ 27,000    
Glass surrounds to vanitary units item @ 5,000   
Miscellaneous architectural metalwork item @ 6,000   
    
Sanitary fittings24,20040.48
    
Sanitaryware and fittings; allowance 6050 m² @ 4    
    
Disposal Installations30,3005.010.61
    
Waste, soil and vent pipework 6050 m² @ 2   
Rainwater installation 6050 m² @ 3   
    
Hot and cold water installations67,30011.121.35
    
Hot and cold water pipework to landlord's areas including mains water service 6050 m² @ 5   
Hot water distribution pipework in plant rooms item @ 22,000    
Roof-mounted condensing boiler item @ 15,000    
    
Space heating air treatment and ventilation398,00065.797.96
    
Air handling units, chillers; ductwork, pipework, insulation 6050 m² @60   
Toilet extract ventilation item @ 15,000   
Cooling and ventilation installations to common areas item @ 20,000   
    
Electrical installation275,90045.65.52
    
Mains and sub-mains distribution 6050 m² @ 20   
Small power to landlord's areas 975 m² @ 15   
Electrical supplies to mechanical plant item @ 17,500   
Lighting to landlord's areas 975 m² @ 50   
External feature lighting item @ 5,000   
External lighting generally item @ 65,000   
Electric trench heating to common areas Item @ 4,000   
    
Gas installations10,0001.650.2
    
Incoming gas supply item @ 10,000   
    
Lift installations25,0004.130.5
    
Ten-person hydraulic lift serving two floors 1 @ 25,000   
    
Protective installations8,5001.40.17
    
Lightning protection item @ 6,000    
Earthing and bonding item @ 2,500   
    
Communication installations36,30060.73
    
Fire alarm and smoke detection 6050 m² @ 5   
Disabled WC alarm system item @ 2,000   
Allowance for containment item @ 4,000   
    
Specialist installations90,80015.011.82
    
BMS controls 6,050 m² @ 15   
    
Builder’s work in connection 10,0001.650.2
    
Forming holes and chases etc. Allowance @ 1% Item @ 10,000   
    
Preliminaries 841,700139.1216.83
    
Management costs, site establishment and site supervision. Contractor's preliminaries, overheads and profit @ 17% Item @ 702,000   
Testing and commissioning of building services installations Item @ 15,000   
Allowance for design reserve @ 3% Item @ 124,700   
    
Total construction cost: building only 5,000,000826.43100
(Square metre rate based on GIFA)
Cost of fit-out to category A
 element costcost/m² GFA £% of total cost
    
Wall finishes75,70014.844.95
    
Emulsion paint to walls; generally Item @ 20,000   
Plasterboard lining 740 m2 @ 65    
Plasterboard column casings 80 @ 95    
    
Floor finishes245,60048.1616.05
    
Raised access floors; medium grade 5100 m2 @ 28   
Carpet tiles 5100 m2 @ 18   
Softwood skirtings; painted 1100 m @ 10   
    
Ceiling finishes140,50027.559.18
    
Mineral fibre tile suspended ceiling; exposed grid 5100 m2 @ 20   
Bulkheads and margins 550 m @ 70   
    
Space heating, air treatment and ventilation510,00010033.33
    
Four pipe fancoils; hot and cold water distribution, ductwork and flexible connections, grilles and diffusers; power supply to FCUs 5100 m2 @ 100   
    
Electrical installation255,0005016.67
    
Lighting, emergency lighting and lighting control 5100 m2 @ 35    
Small power 5100 m2 @ 15    
    
Protective installations 3,0000.590.2
    
Earthing and bonding item @ 3,000   
    
Communication installations25,50051.67
    
Fire detection and alarm system 5100 m2 @ 5    
    
Builder’s work in connection8,0001.570.52
    
Forming holes and chases etc. Allowance @ 1% Item @ 8,000   
    
Preliminaries266,70052.2917.43
    
Management costs, site establishment and site supervision. Contractor's preliminaries, overheads and profit @ 17% Item @ 213,700   
Testing and commissioning of building services installations Item @ 15,000   
Allowance for design reserve @ 3% Item @ 38,000   
    
Total cost: category A fit-out only1,530,000300100
(Square metre rate based on NIFA)
Cost of external works
 element costcost/m² GFA £% of total cost
    
Site works506,00083.6456.86
    
Concrete block pavings 6100 m² @ 35   
Granite sett pavings 1250 m² @ 90   
Precast concrete paving slabs 970 m² @ 40   
Granite chippings 665 m² @ 30   
Precast concrete edgings 100 m @ 10   
Precast concrete kerbs 1490 m @ 30   
Retaining walls; facing brick 35 m @ 155   
Tree grilles 27 @ 1,100   
Miscellaneous external works item @ 10,000   
Allowance for topsoiling, turfing, planting item @ 30,000   
    
Drainage136,00022.4815.28
    
Foul and surface water drain runs 850 m @ 45   
Foul and surface water manholes 18 @ 800   
Sewer and surface water drainage connection item @ 6,000   
Road gullies 35 @ 200   
Petrol inteceptors 2 @ 4,000   
Surface water attenuation; storage chambers 13 @ 4,800   
    
External services100,00016.5311.24
    
Water connection charge item @ 6,000   
Electricity connection charge item @ 30,000   
Gas connection charge item @ 18,000   
Builders work in connection with external services including service trenches and access chambers item @ 46,000    
    
Preliminaries148,00024.4616.63
    
Management costs, site establishment and site supervision. Contractor's preliminaries, overheads and profit @ 17% item @ 126,100   
Allowance for design reserve @ 3% item @ 22,300   
    
Total construction cost: external works only 890,000147.11100
(Square metre rate based on GIFA)
Location factors
Outer London1.03
South-east1.00
South-west0.97
East Midlands0.93
West Midlands0.93
East Anglia0.97
Yorkshire and Humberside0.95
North-west0.94
Northern0.94
Scotland0.92
Wales0.91
Northern Ireland0.75