- News
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- Building the Future
- Jobs
- Data
- Subscribe
- Events
2024 events calendar
Explore nowBuilding Awards
Keep up to date
- Building Boardroom
All the latest updates on building safety reform
2024 events calendar
Explore nowBuilding Awards
Keep up to dateCapital costs for the three options | |||
Option 1 (£) | Option 2 (£) | Option 3 (£) | |
Renew or refurbish escalators | 350 000 | 750 000 | 350 000 |
Re-clad escalators | 100 000 | included in above | 100 000 |
Strip out existing escalators | N/A | 50 000 | N/A |
Remove and reinstate facade for escalator removal | N/A | 20 000 | N/A |
Miscellaneous building works | 9 700 | 28 800 | 9 700 |
New power supplies | 14 500 | 14 500 | 14 500 |
Testing, commissioning and subcontract preliminaries | 23 710 | 43 165 | 23 710 |
Sub-total – new installation works | 497 910 | 906 465 | 497 910 |
Main contractor’s preliminaries, overheads, profit and attendance | 87 134 | 158 631 | 87 134 |
Builders work in connection | included | included | included |
Professional fees | 59 749 | 108 776 | 59 749 |
Sub-total | 644 793 | 1 173 872 | 644 793 |
Less capital allowances relief | (159 783) | (290 973) | (159 783) |
Total capital cost | 485 011 | 882 899 | 485 011 |