Keep up to dateCost information | ||
Element | Total cost of element (£) | Cost/m2 (£) (gfa is 8107 m2) |
substructure | 323 283 | 40 |
frame | 96 332 | 12 |
upper floors | 263 823 | 33 |
roof | 643 674 | 79 |
stairs | 82 001 | 10 |
external walls | 1 229 841 | 152 |
windows and external doors | 124 354 | 15 |
internal walls and partitions | 292 221 | 36 |
internal doors | 327 148 | 40 |
wall finishes | 183 547 | 23 |
floor finishes | 333 748 | 41 |
ceiling finishes | 156 683 | 19 |
painting and decorating | 83 612 | 10 |
fittings and furnishings | 40 000 | 5 |
sanitary appliances | 174 581 | 22 |
mechanical installations | 2 730 000 | 337 |
electrical installations | 1 148 138 | 142 |
lift and conveyor installations | 206 183 | 25 |
special installations | 488 250 | 60 |
builders work in connection with services | 204 976 | 25 |
external works | 169 264 | 21 |
preliminaries | 1 383 237 | 171 |
total | 10 684 898 | 1 318 |