Keep up to dateKey performance indicators | ||
KPI | Gleeson’s benchmark | actual score |
Client* satisfaction with product | 8 | 7.7 |
Client* satisfaction with service | 8 | 7 |
Defects | 8 | 6.8 |
(this does not measure defects on handover but defects and delays at eight key build stages) | ||
Predictability of cost (design) | 0% | 0.38% |
Predictability of time (construction) | 0% | 1.3% |
Safety | 997 per | 33.1 per |
(target based on HSE annual target) | 100 000 employed | 100 000 employed |
Sustainability (waste produced) | 7167 m3 | 440 m3 |
(target based on average of 33 m3 of waste produced per £10 000 project expenditure) | ||
* Gleeson is the client. |