Keep up to dateCost breakdown for Portcullis House | ||
The MPs’ building is being built by construction management. The package contractors are employed directly by client the Houses of Parliament, with Laing managing their work. | ||
Works pacakge | Contractor | £m |
Cranage | Hewden Stewart Wolff | 1.4 |
Multipurpose workforce | Clipfine | 0.9 |
Site hoists | Maxxiom | 0.1 |
Site accommodation | DBS International | 0.1 |
Gantry steelwork | Balguard Engineering | 0.1 |
Welfare accommodation | Clipfine | 0.1 |
Site electrics | Wingate Electrics | 0.2 |
Site security | Pinkerton Security Services | 1 |
External works | Not yet appointed | 2.3 |
Borehole remedial works | European Geophysical Services | 0.1 |
Granite walling and plinths | Natural Stone Products | 0.5 |
Precast concrete arches | Hibex NV | 0.5 |
Sandstone columns | Natural Stone Products | 3 |
Precast concrete units | Loveld NV | 5.2 |
Core stairs | Littlehampton Welding | 0.3 |
Erection | O’Rourke Civil Engineering | 5 |
Arch metalwork | Andaray | 0.3 |
Main roof | Watson Steel | 13.2 |
Fenestration | Seele-Alvis Fenestration | 33 |
Blinds | The Louvre Blind Co. | 1.2 |
Courtyard roof | Portal | 3 |
External glazed screens | Not yet appointed | 1.9 |
Internal glazed screens | Portal | 1.5 |
Canopies and valances | Not yet appointed | 0.3 |
Main staircase | Not yet appointed | 0.1 |
Link bridge | Not yet appointed | 0.3 |
General builder | Duffy Construction | 0.5 |
Joinery level 1 | Trollope & Colls Elliott | 2 |
Joinery level 2-4 | Swift Horsman | 4.5 |
Joinery level 5-6 | Ruddy Joinery | 2 |
Partitions | Dove Brothers | 3.3 |
Raised floors | Durabella | 2 |
Floor tiles | Not yet appointed | 0.9 |
Courtyard paving | Not yet appointed | 1.2 |
Courtyard planting | Not yet appointed | 0.2 |
Core areas fit-out | Trollop Colls Elliot | 3.6 |
Catering area – builder’s work | Not yet appointed | 1.1 |
Catering equipment | AF Designs | 0.8 |
Mechanical services | Crown House Engineering | 10 |
Electrical services | Kvaerner Rashleigh Weatherfoil | 3.5 |
Telecommunications | Not yet appointed | 0.3 |
Data cabling | Not yet appointed | 0.4 |
Security | Not yet appointed | 0.3 |
Annunciators | Not yet appointed | 0.3 |
Lifts and hoists | Hammond and Champness | 1.1 |
Escalators | Otis | 0.2 |
Facade cleaning – installation | Gebr-Kupfer | 0.4 |
Water and drainage connection | Thames Water Utilities | 0.1 |
Electricity connection | London Electricity | 0.1 |
Office desks, tables and filing cabinets | Not yet appointed | 1.3 |
Office chairs | Not yet appointed | 0.6 |
Office loose equipment | Not yet appointed | 0.2 |
Leather seats | Not yet appointed | 0.2 |
Worktops and shelves | Not yet appointed | 0.4 |
Select committee rooms tables | Not yet appointed | 0.1 |
Easy chairs | Not yet appointed | 0.2 |
Select committee rooms chairs | Not yet appointed | 0.1 |
Shop furniture and fittings | Not yet appointed | 1 |
Restaurant furniture and fittings | Not yet appointed | 0.5 |
Reception area furniture and fittings | Not yet appointed | 0.1 |
Subtotal | 119.1 | |
Small value prelim packages | 2.7 | |
Mock-ups and testing | 0.7 | |
Package contingencies, small-value packages, orders yet to place and post-contract variations | 23.5 | |
Construction, including prelims | 146 | |
Professional advisers – design team, cost consultant, project manager, construction manager and lawyer | 42 | |
Work by Jubilee Line Extension | 1 | |
Insurance | 1 | |
VAT | 29 | |
Subtotal | 219 | |
Risk provision, general contingencies and JLE delay | 31 | |
Total | 250 |