Keep up to dateWhy is it costing so much? | |
Land purchase cost | £106m |
Consultants fees | £60m |
Construction costs | £326m |
Construction contingencies | £30m |
FA financing and rolled-up interest | £20m |
FA contingent support, against performance of the business plan | £80m |
Section 106 agreement to build two roads from the North Circular and a boulevard to the stadium | £20m |
Management costs for seven years and insurances | £18m |
TOTAL | £660m |