Student accommodation
Element cost (£)cost/m2 gfa (£)% of total cost
Substructure164072.297.22
Piling, deep strip foundations and ground-bearing slab; reduced level dig, disposal    
item @ 1,229,000   
Modules13,210582.7958.18
Bedroom modules, fully furnished, complete with en-suite bathroom, including all services to final connections with below-ground installation   
750 @ 10,500   
Kitchen modules, fully fitted, including all services to final connections with below-ground installation   
125 @ 13,500   
Stair modules   
30 @ 11,500   
Envelope4130182.2818.20
External walls – terracotta rainscreen; including allowances for framing and interfaces with modules   
17,000 m2 @ 140   
Roof – timber structure, roof tiles, rainwater goods   
6250 m2 @ 115   
Joinery generally1908.240.82
Internal and external doors, canopies   
item @ 140,000   
Finishes generally1520 66.946.68
Wall, floor and ceiling finishes to corridors only   
item @ 88,000   
Ancillary buildings140061.776.17
Allowance for conventionally constructed amenities buildings   
item @ 1,050,000   
Contingencies620 27.352.73
Allowance based on 3%   
item @ 465,000   
Total construction cost – building only22,7101001.66100
Reported costs are current in 1st quarter 2002, based on a location in south-east England. Preliminaries are included in the rates. The costs exclude site remediation costs, infrastructure and external works, professional fees and VAT   
Amphion project
Element cost (£)cost/m2 gfa (£)% of total cost
Substructure4500 53.299.37
Strip foundations and ground bearing slab; reduced level dig, disposal
item @ 162,000   
Frame, upper floors and partitions9110 107.9318.97
Timber frame panels, external wall panels, upper floors, roof structure and internal partitions
item @ 328,100   
Roof2840 33.655.91
Roof coverings; concrete roof tiles, rainwater goods
item @ 102,300   
External wall cladding5630 66.7111.73
Single skin outer brick wall   
item @ 202,800   
Joinery generally6560 77.7313.66
Stairs   
item @ 36,200   
Windows and external doors; timber; site finished
item @ 150,100   
Internal doors   
item @ 50,000   
Finishes generally8910 105.4918.54
Wall, floor and ceiling finishes   
item @ 320,700   
Furniture and fittings1540 18.193.20
Fixtures and fittings generally   
item @ 55,300   
Services generally8940 105.9218.62
Sanitary fittings   
item @ 33,800   
Plumbing   
item @ 89,800   
Heating and ventilation   
item @ 126,500   
Electrical installation   
item @ 71,900   
Total construction cost – building only48,030568.91 100
External works11,140 131.91
Drainage, service trenches, lighting, drives, parking areas and paved areas, soft landscape, screen walls and fencing
item @ 401,000   
Adoptable works6970 82.57
Roads, footpaths, sewers, street lighting and street furniture
item @ 251,000   
Service mains and connections3830 45.39
item @ 138,000   
Overall construction cost 69,970828.78
Reported costs are current in 1st quarter 2002, based on a location in southern England. Allowances for preliminaries and contingencies are included in the rates. The costs exclude site preparation costs, off-site works including services diversions, surveys, professional fees and VAT