Capital expenditure allocations in the 2000 comprehensive spending review
Year£m
2000/12232
2001/22512
2002/33012
2003/43812
Regional variation
Inner London1.08
Outer London1.02
South West0.95
East Midlands0.92
West Midlands0.93
East Anglia0.93
Yorkshire & Humberside 0.88
North West0.92
North0.91
Scotland0.89
Wales0.87
Northern Ireland0.79
Summary costs of secondary schools and colleges
Average (£/m2 gifa)Low range (£/m2 gifa) High range (£/m2 gifa)
Classroom blocks 875 605 1100
Laboratories 900 745 1150
Craft, design and technology 920 720 1130
Music 1140 750 1570
Sixth-form/tertiary 930 690 1185
All secondary schools and colleges915 650 1160
School science block cost breakdown
element cost (£)cost/m2 gfa (£)% of total cost
Substructure112,50077.058.16
Reinforced insitu concrete ground beams and suspended slab; vapour barrier; hardcore, excavation and disposal 520 m2 @ 140   
CFA piling; average 15m deep; testing; trimming pile tops 65 @ 610   
Frame103,90071.167.54
Structural steel frame; standard and cellular beam sections; based on allowance of 50kg/m2; erection 74 @ 1100   
Intumescent paint, one-hour fire resistance 1500 m2 @ 15   
Upper floors41,40028.363.00
Composite construction; 140 thick reinforced concrete on metal deck; power floating 940 m2 @ 44   
Roof66,40045.484.82
Galvanized steel roofing; low pitch; vapour barrier, insulation, secret fixings, plastisol coating; including allowances for edges, eaves and gutters; 2 access hatches 540 m2 @ 96   
Single layer PVCu roofing; membrane; insulation; metal deck; boundary work and gutters 80 m2 @ 110   
Mansafe system Item @ 5800   
Stairs22,70015.551.65
Contractor designed precast concrete stairs and    
4 @ 2800   
Balustrades; 1.1m average high; galvanized steel half landings; 3.4m rise   
balustrade and handrail 43 m @ 165   
Handrails; galvanized steel 40 m @ 110   
External walls89,20061.106.47
Cavity wall construction; facing brick; fair face blockwork; dpcs; insulation; allowance for sills and lintels 750 m2 @ 90   
Metal cladding; colour-coated profiled sheet, insulation and liner panel, cladding rails and blockwork 65 m2 @ 180   
Allowance for abutments, edge details and copings Item @ 10,000   
Windows and external doors94,30064.596.84
Proprietary aluminium framed, double-glazed windows; powder-coated finish 95 m2 @ 300   
Curtain walling; aluminium framed stick system with sealed double-glazed units 160 m2 @ 320   
Extra for sloping curtain walling Item @ 3000   
Entrance door; aluminium framed glazed door; automatic operation 1 @ 5000   
External doors; aluminium framed; polyester-coated; to match windows 4 @ 1650   
Internal walls and partitions31,90021.852.31
Partitions; 100 solid/hollow facing blockwork (average rate) 1225 m2 @ 25   
Cubicle partitions; laminated plastics 3 @ 440   
Internal doors33,60023.012.44
Flush doors; solid core; paint grade; vision panels; softwood frame; 30/30 fire resistance; stainless steel door furniture; decorations 56 @ 500   
Extra for; glazed side panels 17 @ 330   
Wall finishes20,60014.111.49
Dry lining; column encasement Item @ 3000   
Ceramic tiles; full height in WCs, allowance in laboratories 215 m2 @ 40   
Painting blockwork; 1 mist, 3 full coats emulsion paint 3000 m2 @ 3   
Floor finishes52,60036.033.82
Carpet; to general areas; levelling screed 600 m2 @ 22   
Sheet flooring; linoleum to corridors 160 m2 @ 22   
Sheet flooring; high quality vinyl sheet 560 m2 @ 35   
Rubber flooring; to stairwells; nosings 140 m2 @ 44   
Softwood skirting 900 m @ 9   
Allowance for entrance barrier matting Item @ 2000   
Ceiling finishes23,50016.101.71
Suspended ceilings; resin bonded glasswool tile; exposed grid 950 m2 @ 22   
Painting to soffits; generally 510 m2 @ 5   
Furniture and fittings95,00065.076.89
Fixed furniture and equipment; whiteboards and pinboards; worktops in steel, laminate and acrylic; specialist workstations; racking and storage; fume cupboard; laboratory sinks and accessories; gas outlets and socket outlets Item @ 90,000   
Window boards Item @ 3000   
Statutory and orientation signage Item @ 2000   
Sanitary fittings13,4009.180.97
WCs, urinals, washhand basins, fittings; cleaners’ sinks; complete (average rate) 7 @ 280   
Extra for, fittings for disabled WCs 2 @ 400   
Allowance for access panels Item @ 3000   
Hand dryers Item @ 2000   
Disposal installations14,60010.001.06
Waste, soil and vent installation; PVCu pipework and fittings 1460 m2 @ 10   
Water installations32,10021.992.33
Mains water; cold water storage and distribution, hot water calorifier, pumps and distribution pipework; including distribution to laboratories 1460 m2 @ 22   
Space heating and air treatment120,80082.748.77
Heating installation; gas supply, heat source; LPHW distribution; radiators, mild steel pipework 1460 m2 @ 30   
Localised comfort cooling; heat pump, installation to computer suite Item @ 12,000   
Supply and extract installation to laboratories and classrooms Item @ 54,000   
Toilet extract installation Item @ 6000   
Dust extract installation Item @ 5000   
Electrical installations103,70071.037.53
Mains and sub-mains installation 1460 m2 @ 16   
Small power installation 1460 m2 @ 18   
Lighting and general luminaires; emergency lighting 1460 m2 @ 35   
Power supply installation to mechanical equipment Item @ 3000   
Gas installation90006.160.65
Laboratory gas supply; terminals included in fixed furniture and fittings (120 points) Item @ 9000   
Lift installation30,00020.552.18
4 person electro-hydraulic lift serving 3 floors; 0.4 m/s Item @ 30,000   
Protective installations17001.160.12
Lightning protection; earthing and bonding Item @ 1700   
Communications installation47,80032.743.47
Fire alarm installation; smoke detectors; call points 1640 m2 @ 12   
Disabled alarm Item @ 600   
Telephone and data wireways; Cat 5E data wiring Item @ 12,500   
Security installation; intruder detection, CCTV, etc Item @ 15,000   
Special installations23,30015.961.69
Building management system 1640 m2 @ 12   
Compressed air installation (20 points) Item @ 3600   
Builder's work in connection11,9008.150.86
Forming holes, chases, etc Allow 3% Item @ 11,900   
Preliminaries and contingencies182,100124.7313.22
Testing and commissioning of services; record drawings Item @ 2500   
Management costs, site establishment and site supervision   
Allow 10% Item @ 119,600   
Contingency sum Allow 5% Item @ 60,000   
Total construction cost – building only1,378,000943.85100
School craft, design and technology block
element cost (£)cost/m2 gfa (£)% of total cost
Substructure65,70065.056.04
Reinforced insitu concrete foundations and ground slab, including service trench; vapour barrier; hardcore, excavation and disposal 885 m2 @ 62   
Precast concrete flooring; beam and block decking; over service trench; 150 thick 40 m2 @21    
Masonry work below dpc; blockwork and facing brickwork Item @ 10,000   
Frame63,10062.485.80
Structural steel frame; standard sections; based on allowance of 30 kg/m2; erection 28 t @1100   
Intumescent paint, one-hour fire resistance 600 m2 @ 15   
Glulam beams; curved rafters; purlins; finishes (average rate) 375 m @ 62   
Upper floors60005.940.55
Mezzanine deck; precast, prestressed concrete floor units; 150 thick 125 m2 @ 48   
Roof146,100144.6513.43
Standing seam aluminium roofing; structural deck, vapour barrier, insulation, roof sheet; including boundary work and gutters; paint finish to soffit 1090 m2 @ 114   
Single-layer PVCu roofing; membrane; insulation; plywood; boundary work and rainwater outlets 110 m2 @ 100   
Rooflights; sunpipe tubing; 800 long 7 @ 830   
Mansafe system Item @ 5000   
Stairs85008.420.78
Steel framed stair with hardwood treads and landings; 3.3 m rise in three flights Item @ 2500   
Balustrades; 1.1 m average high ; galvanized steel balustrade and handrail 50 m @ 120   
External walls69,00068.326.35
Cavity wall construction forming plinth; facing brickwork Item @ 1000   
Cavity wall construction; two leaves blockwork, insulation, sand cement render 35 m2 @ 90   
Timber cladding; ship-lapped western red cedar; breather membrane, battens, cladding rails, insulation, blockwork backing wall; including boundary work 360 m2 @ 180   
Windows and external doors109,200108.1210.04
Proprietary aluminium framed, double-glazed windows, doors and solid aluminium faced panels; powder-coated finish 325 m2 @ 300   
Extra for operating gear to clerestory windows Item @ 3000   
External doors; Cedar board finished flush doors to match cladding; ironmongery 8 @ 1090   
Internal walls and partitions37,50037.133.45
Partitions; 100/140 blockwork (average rate) 630 m2 @ 25   
Glazed screens; powder-coated aluminium frames; double-glazed units; radiused head 52 m2 @ 270   
Allowance for small areas of panelling, partitions and trims generally Item @ 6500   
Cubicle partitions; laminated plastics 3 @ 400   
Internal doors14,60014.461.34
Flush doors; laminate faced solid core; vision panels; softwood frame; 30/30 fire resistance; stainless steel door furniture; decorations 28 @ 500   
Extra for; glazed side panels 6 @ 100   
Wall finishes21,30021.091.96
Dry lining; column encasement Item @ 1000   
2 coat plasterwork 1450 m2 @ 10   
Ceramic tiles; full height in WCs, allowance in laboratories 20 m2 @ 40   
Painting blockwork; 1 mist, 3 full coats emulsion paint 1650 m2 @ 3   
Floor finishes42,80042.383.94
Allowance for access floor to service trench Item @ 3000   
Floor substrate for underfloor heating; 70 thick sand cement screed, insulation and fabric reinforcement 805 m2 @ 10   
Sand cement screed to service trench 80 m2 @ 17   
Ceramic tiling; skirting 110 m2 @ 40   
Vinyl sheet; skirting 525 m2 @ 29   
Carpet; painted softwood skirting 345 m2 @ 24   
Allowance for entrance mats Item @ 2500   
Ceiling finishes83008.220.76
Plasterboard ceiling; skim coat and emulsion 240 m2 @ 18   
Soffit linings to clerestory windows Item @ 4000   
Furniture and fittings91,00090.108.37
Fixed furniture and equipment; whiteboards and pinboards; worktops in laminate-faced MDF and Iroko; cupboards, racking and shelving Item @ 83,000   
Window boards Item @ 6000   
Statutory and orientation signage Item @ 2000   
Sanitary fittings18,10017.921.66
WCs, urinals, washhand basins, fittings; cleaners' sinks; complete (average rate) 14@250   
Stainless steel sinks in teaching areas 15@460   
Extra for, fittings for disabled WCs 1@400   
Allowance for pre-plumbed panel lining system Item@7300   
Disposal installations20,20020.001.86
Waste, soil and vent installation; PVCu pipework and fittings 1010 m2 @ 20   
Water installations22,20021.982.04
Mains water; cold water storage and distribution, hot water calorifier, pumps and distribution pipework; including distribution to laboratories 1010 m2 @ 22   
Space heating and air treatment53,90053.374.96
Heating installation; gas supply, heat source; LPHW distribution, mild steel pipework, connections to underfloor heating system 1010 m2 @ 23   
Extra for; underfloor heating distribution 755 m2 @ 30   
Extract installation generally Item @ 8000   
Electrical installations88,60087.728.15
Mains and sub-mains installation 1010 m2 @ 14   
Small power installation 1010 m2 @ 30   
Lighting and general luminaires; emergency lighting 1010 m2 @ 35   
Power supply installation to workshop equipment Item @ 7300   
Power supply installation to mechanical equipment Item @ 1500   
Gas installation20001.980.19
Teaching equipment gas supply Item @ 2000   
Protective installations3,7003.660.34
Lightning protection; earthing and bonding Item@3700   
Communications installation31,10030.792.86
Fire alarm installation; smoke detectors; call points 1010m2 @ 12   
Class change bell Item @ 1000   
Telephone and data wireways; internal telephone system Item @ 11,000   
Security installation; intruder detection, CCTV etc Item @ 7000   
Special installations13,10012.971.20
Building management system 1010 m2 @ 8   
Oxyacetylene installation  Item @ 5000   
Builder's work in connection76007.520.70
Forming holes, chases, etc Allow 3% Item @ 7600   
Preliminaries and contingencies143,900142.4813.23
Testing and commissioning of services; record drawings Item @ 2500   
Management costs, site establishment and site supervision Allow 10% Item @ 94,400   
Contingency sum Allow 5% Item @ 47,000   
Total construction cost – building only1,087,5001076.75100