- News
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- Building the Future
- Jobs
- Data
- Subscribe
- Events
2024 events calendar
Explore nowBuilding Awards
Keep up to date
- Building Boardroom
All the latest updates on building safety reform
2024 events calendar
Explore nowBuilding Awards
Keep up to dateHot rates: Preliminaries | ||
£ per week | % of total prelims | |
£5m greenfield industrial building, Midlands, 26-week contract | ||
Contract guarantee bond | 200 | 2.2 |
Name board | 30 | 0.3 |
Management and staff | 5000 | 54.7 |
Site accommodation | 350 | 3.8 |
Power, lighting and water | 400 | 4.4 |
Rubbish disposal, cleaning, drying and protection | 600 | 6.6 |
Additional services and facilities | 300 | 3.3 |
Small plant and tools | 60 | 0.7 |
Mechanical plant | 360 | 3.9 |
Temporary roads and hardstandings | 1350 | 14.8 |
Access scaffolding | 200 | 2.2 |
Hoardings, fans, fencing | 135 | 1.5 |
Additional temporary works | 150 | 1.6 |
TOTAL | 9135 | 100 |
Preliminaries as % of other works | 5% | |
£500,000 refurbishment, northern England, 30-week contract | ||
Contract guarantee bond | 25 | 1.2 |
Name board | 15 | 0.7 |
Management and staff | 1200 | 57.1 |
Site accommodation | 90 | 4.3 |
Power, lighting and water | 45 | 2.1 |
Rubbish disposal, cleaning, drying out and protection | 115 | 5.5 |
Additional services and facilities | 25 | 1.2 |
Small plant and tools | 25 | 1.2 |
Mechanical plant | 35 | 1.7 |
Temporary roads and hardstandings | 0 | 0 |
Access scaffolding | 500 | 23.8 |
Hoardings, fans, fencing | 15 | 0.7 |
TOTAL | 2090 | 100 |
Preliminaries as % of other works | 15% | |
£1m single-storey school, East Anglia, 45-week contract | ||
Contract guarantee bond | 35 | 2.2 |
Name board | 10 | 0.6 |
Management and staff | 800 | 49.8 |
Site accommodation | 75 | 4.7 |
Power, lighting and water | 70 | 4.4 |
Rubbish disposal, cleaning, drying out and protection | 90 | 5.6 |
Additional services and facilities | 100 | 6.2 |
Small plant and tools | 25 | 1.6 |
Mechanical plant | 160 | 10 |
Temporary roads and hardstandings | 40 | 2.5 |
Access scaffolding | 200 | 12.5 |
Hoardings, fans, fencing | 0 | 0 |
Additional temporary works | 0 | 0 |
TOTAL | 1605 | 100 |
Preliminaries as % of other works | 8% | |
£3.5m sports centre, London, 45-week contract | ||
Contract guarantee bond | 115 | 1.2 |
Name board | 15 | 0.2 |
Management and staff | 5800 | 58.6 |
Site accommodation | 330 | 3.3 |
Power, lighting and water | 350 | 3.5 |
Site security | 570 | 5.8 |
Additional services and facilities | 265 | 2.7 |
Small plant and tools | 70 | 0.7 |
Mechanical plant | 440 | 4.4 |
Temporary roads and hardstandings | 200 | 2.0 |
Access scaffolding | 1500 | 15.2 |
Hoardings, fans, fencing | 235 | 2.4 |
TOTAL | 9890 | 100 |
Preliminaries as % of other works | 15% |
Price changes | |
% change since spring 2001* | |
Hardcore | +9% |
Insitu concrete | +10% |
Steel reinforcement | +3% |
Common bricks | +9% |
Engineering bricks | +5% |
Concrete blocks | +6% |
Natural stone rubble | +4% |
Precast concrete lintels | +8% |
Structural steel | -6% |
Sawn softwood | +5% |
Clay roof coverings | -2% |
Concrete roof coverings | +2% |
Natural slate-roof coverings | -2% |
Plasterboards | -2% |
MDF/Chipboard linings | +3% |
Standard softwood doors and windows | +5% |
Glazing | +10% |
Paints | +6% |
Insulation | +2% |
Stone pavings | +3% |
* since the publication of Spon’s 2002 Price Books |
Materials prices | |
Key Indicators | % change over last 12 mths (April 2001-April 2002) |
Retail Prices Index | |
Headline rate (RPI) | +1.5 |
All items, excluding mortgage interest payments (RPIX) – government’s target index | +2.3 |
All items, excluding mortgage interest payments and indirect taxes (RPIY) | +2.5 |
Harmonised Index of Consumer Prices (HICP) | +1.3 |
Industry generally | |
Materials and fuels purchased bymanufacturing industry | -3.6 |
of which materials | -3.9 |
fuel | -1.4 |
Materials and fuels purchased by manufacturing industry, excluding food, beverages, tobacco and petroleum | -4.3 |
Output prices of manufactured products | +0.2 |
Output prices of manufactured products excluding food, beverages, tobacco and petroleum | +0.2 |
Construction industry | |
Construction materials | +1.0 |
Housebuilding materials | +0.9 |
Machinery and equipment (UK manufacture) | +0.9 |
Electrical machinery and apparatus (UK manufacture) | +0.6 |
Source: Office for National Statistics (March/April 2002 figures provisional) | |
Notes: The ONS category “Machinery and Equipment” includes mechanical engineering items such as pumps, taps, valves, lifts, cooling and ventilation equipment. “Electrical machinery and apparatus” includes electrical engineering materials such as electricity distribution and control apparatus, wires and cables and lighting equipment. |
Price adjustment formulae for construction contracts | |||
% change July 2001-March 2002 | % change July 2001-March 2002 | ||
Softwood carcassing and structural members | +2.2 | Metal: decking | -6.1 |
Cladding and covering: sheet and tile | +2.1 | Cladding and covering: coated steel | -4.2 |
Cladding and covering: lead | +4.8 | Cladding and covering: aluminium | -3.0 |
Sanitary appliances | +2.6 | Cladding and covering: zinc | -4.1 |
Pipes and accessories: spun and cast iron | +4.9 | Raised access floors | -4.0 |
Pipes and accessories: steel | +2.9 | Finishes: rigid tiles and terrazzo work | -7.3 |
Pipes and accessories: plastics | +2.6 | Insulation | -2.4 |
Pipes and accessories: aluminium | +3.3 | ||
Aside from the first three items, the remaining work categories registering price rises have a plumbing labour input. Plumbers in England and Wales received a substantial wage increase in September last year, creating a 5.7% increase in labour costs. | |||
Almost all those shown in the table have a significant metal content. ONS statistics show that imported metal prices fell 14% between September 2000 and November 2001. Since the end of last year, metal prices have stabilised, even staging a minor recovery, though some are beginning to fall in price again. |
Wage agreement summary | ||||
Operatives | Agreement body | Wage rates effective since | Details in | Date of next review |
Builders and civil engineering operatives | Construction Industry Joint Council | 25 June 2001 | Cost update 1 June 2001 Spon’s Architects’ and Builders’ Price Book 2002 | 24 June 2002 (third part of three-year agreement – see above) |
Building and Allied Trades Joint Industrial Council (BATJIC) | 11 June 2001 | Cost update 1 June 2001 Spon’s Architects’ and Builders’ Price Book 2002 | 10 June 2002 (see above) | |
Plumbers | The Joint Industry Board for Plumbing Mechanical Engineering Services in England and Wales | 3 September 2001 | Cost update 31 August 2001 | 2 December 2002 (second part of two-year agreement) |
Scottish and Northern Ireland Joint Industry Board for the Plumbing Industry | 8 April 2002 | Cost update 8 March 2002 | 28 October 2002 (third part of four-part, two-year agreement) | |
Heating and ventilation operatives | Joint Conciliation Committee of the Heating, Ventilating and Domestic Engineering Industry | 3 September 2001 | Cost update 31 August 2001 Spon’s Mechanical and Electrical Services Price Book 2002 | 7 October 2002 (third part of three-year agreement) |
The Joint Industry Board for the Electrical Contracting Industry | 7 January 2002 | Cost update 9 Nov 2001 | 6 January 2003 (second part of three-year agreement) | |
Electricians | Scottish Joint Industry Board for the Electrical Contracting Industry | 7 January 2002 | Cost update 8 March 2002 | 6 January 2003 (second part of three-year agreement) |