Cost breakdown
Element costcost/m2 gfa £% of total cost
Substructure13,954,000117.805.45%
Allowance for breaking out existing slabs and retaining walls Item @ 250,000    
Allowance for preparatory work and dewatering all of the excavations Item @ 600,000    
Foundations: large diameter bored piles, for example 40 m deep; 2 m thick ground slab 2,600 m2 @ 1,500    
Extra for three-level basement construction: part secant piled walls, part diaphragm walls; insitu concrete frame and floors; waterproofing; drainage 7,800 m2 @ 1,000    
Allowance for removal of obstructions Item @ 250,000    
Allowance for treatment of contaminated surfaces 2,600 m2 @ 40    
Allowance for temporary works Item @ 750,000    
Allowance for lift pits, escalator pits, tower crane bases, etc Item @ 300,000    
Frame41,928,000353.9716.38%
Structural steel frame to upper floors, based on 200 kg/m2 overall (avg rate) 22,130 t @ 1,200    
Secondary steelwork for cladding, trimming openings, etc 2,200 t @ 1,600    
Extra for feature steel framing in reception/other areas Item @ 500,000    
Fire protection to frame based on a combination of two-hour boarding and one-hour intumescent spray (avg rate used, based on 20 m2/tonne) 482,600 m2 @ 20    
Allowance for concrete casing or infilling to some columns Item @ 500,000    
Allowance for wind canopy structures Item @ 200,000    
Allowance for additional ductile connections Item @ 1,000,000    
Upper floors8,146,00068.773.18%
Composite floor construction; 130 mm thick reinforced insitu concrete; galvanized steel decking; total design load 4.5 kN/m2 110,650 m2 @ 55    
Extra for 7.5 kN/m2 loading to plant and other areas 10,000 m2 @ 25    
Extra for forming ramps, steps, and so on Item @ 500,000    
Allowance for knock-out panels in upper floors construction Item @ 200,000    
Allowance for lift pits, escalator pits, etc in upper floors construction Item @ 150,000    
Allowance for insulation to edges of floor slabs 8,800 m @ 75    
Extra for intermediate floors to atrium at six-storey intervals Item @ 300,000    
Roof1,657,00013.990.65%
Waterproofing over external slab at ground level (over basements) 124 m2 @ 80    
Composite roof slab construction, with waterproofing, insulation, ballast 2,350 m2 @ 200    
Extra for access paving to 10% of roof area 250 m2 @ 75    
Extra for stone paving to terraces 100 m2 @ 150    
Architectural balustrading to roof terraces 50 m @ 550    
Glazed atrium roof, with opening lights for ventilation/smoke extract; framing 200 m2 @ 1,200    
Allowance for roof feature/screening to roof level plant Item @ 400,000    
Allowance for perimeter safety rails, perimeter detailing & interface details Item @ 250,000    
Allowance for plant bases and base for communication mast Item @ 50,000    
Allowance for roof-level plant enclosures; structural steel frame; profiled aluminium raised seam roof cladding, insulation Item @ 175,000    
Stairs3,086,00026.051.21%
Painted mild steel escape stairs in two straight flights, including all finishes 94 @ 16,000    
Precast concrete stairs serving basements 8 @ 14,000    
Allowance for feature staircases Item @ 900,000    
Steel stairs within retail areas 8 @ 15,000    
Allowance for disabled access provisions Item @ 250,000    
Allowance for ladders and catwalks in plant rooms Item @ 200,000    
External walls61,264,000517.2123.94%
Triple glazed “active wall” facade system: double-glazed outer skin, single-glazed inner skin with opening lights; integral motorised blinds 51,000 m2 @ 875    
Allowance for enhanced articulation in certain areas Item @ 5,000,000    
Double-glazed atrium wall 3,700 m2 @ 1,000    
Double-height glass wall system to ground floor, including all supports 800 m2 @ 1,500    
Glass shop fronts 230 m2 @ 800    
Louvres as external walling to plant floors/roof plant areas 3,100 m2 @ 550    
Solid walls in loading bay/service yard Item @ 50,000    
Unitised metal cladding to exposed core areas, and loading bay 8,000 m2 @ 450    
Metal cladding to soffits Item @ 150,000    
Allowance for entrance canopy/wind canopies Item @ 350,000    
Allowance for mock-ups, testing and so on Item @ 700,000    
External doors916,0007.730.36%
Double-glazed aluminium frame exit and fire escape doors 25 @ 4,000    
High-quality motorised revolving doors and side doors for disabled access 4 @ 150,000    
Shopfront automatic doors 8 @ 7000    
Access doors to roof plant areas Item @ 40,000    
Metal doors in service areas Item @ 30,000    
Motorised security shutters to car park/loading bay entrance (including cladding interfaces) 2 @ 45,000    
Internal walls and partitions7,153,00060.392.80%
Two-hour metal stud partitions around cores 29,100 m2 @ 90    
One-hour metal stud partitions within core areas 17,900 m2 @ 55    
Extra for shaft wall construction Item @ 500,000    
Single-glazed wall around atriums 2,500 m2 @ 700    
Block walls in basements and plant areas 4,200 m2 @ 50    
Block walls dividing retail units 500 m2 @ 60    
Cantilevered glass balustrade around mezzanine 22 m2 @ 1,200    
Allowance for substation enclosure and access Item @ 200,000    
WC cubicles, including doors and ironmongery 450 @ 1,250    
Full height laminate-faced duct access panels to toilets 1,800 m2 @ 150    
Internal doors2,483,00020.960.97%
High quality glazed double doors/side panels to lift lobbies 96 @ 7,000    
Hardwood doors in core areas, fire-rated where necessary (average rate) 575 @ 1,350    
Riser cupboard doors: fire-rated hardwood doorsets 490 @ 1,500    
Metal doors in plant/service areas, 160 @ 1,250    
Allowance for fire-rated access panels Item @ 100,000    
Wall finishes3,400,00028.71.36%
Stone cladding to entrance lobby and lift lobbies 5,120 m2 @ 300    
Allowance for feature wall in main reception Item @ 200,000    
Finish to edges of slabs overlooking reception 22 m @ 300    
Emulsion to core walls/plasterboard partitions & other walls 51,700 m2 @ 5    
GRG circular casings to internal columns in office areas 3,000 m2 @ 175    
Emulsion paint to service areas, plant rooms, facilities offices, storage areas 25,000 m2 @ 5    
Good-quality ceramic tiling to toilets 6,885 m2 @ 100    
Ceramic tiling in cleaners’ cupboards and service areas 1,000 m2 @ 60    
Floor finishes 2,771,00023.391.08%
Granite tiles to main entrance lobby, lift lobbies,    
mezzanine areas and atrium base 4,100 m2 @ 300    
Good-quality ceramic tiles to toilets, lightweight    
concrete to make up levels 4,000 m2 @ 125    
Raised floors to lift lobbies 2,580 m2 @ 37    
Ceramic tiling to cleaners’ cupboards and service areas 350 m2 @ 50    
Raised floor and good-quality carpet tiles to circulation areas 3,820 m2 @ 85    
Epoxy paint on screed to plant and service areas 9,290 m2 @ 25    
Sealer/hardener/wpm/wear course to loading dock,   
service areas, car park 1,700 m2 @ 65    
Allowance for making up levels in other areas Item @ 50,000    
Allowance for linoleum to facilities offices, storage areas, and so on Item @ 30,000    
Entrance mats and matwells Item @ 80,000    
Allowance for sundry floor finishes in other areas Item @ 100,000    
Ceiling finishes1,879,00015.860.73%
Feature ceiling to entrance lobby, mezzanine and lift lobbies 3,900 m2 @ 250    
Non-standard metal suspended ceiling to circulation areas 3,820 m2 @ 100    
Metal suspended ceiling to toilets 4,000 m2 @ 50    
Paint finish to soffit of slabs to plant areas 9,290 m2 @ 10    
Acoustic insulation lining to car park soffit 950 m2 @ 30    
Allowance for other ceiling finishes/detailing Item @ 200,000    
Furniture and fittings4,092,00034.551.60%
Granite vanity tops in toilets 650 m @ 1,100    
Fittings to toilets (including allowance for disabled fittings) 4,000 m2 @ 500    
Wall protection in goods lift lobbies 860 m2 @ 60    
Main reception desk/screen Item @ 100,000    
Main entrance and statutory signage; external signage Item @ 250,000    
Car park bollards, column guards, entrance barriers Item @ 75,000    
Cycle racking and cycle changing area fit-out Item @ 50,000    
Dockmaster/security room fit-outs Item @ 30,000    
Rubbish compactor/bailer Item @ 35,000    
Allowance for main entrance features/fittings/objets d’art Item @ 500,000    
Traffic management system Item @ 35,000    
Allowance for sundry fittings Item @ 250,000    
Sanitary fittings785,0006.630.31%
Allowance for WCs, basins, cleaners’ sinks, urinals (average rate used) 800 @ 700    
Extra for disabled toilets 100 @ 2,000    
Shower installations 20 @ 750    
Water softeners 2 @ 5,000    
Disposal installations1,808,00015.260.71%
Allowance for rainwater disposal 118,450 m2 @ 5    
Soil waste and vent installation 118,450 m2 @ 9    
Extra for drainage to retail units Item @ 150,000    
Water installations1,176,0009.930.46%
Cold water: boosted rising main, bulk storage, treatment, etc 118,450 m2 @ 6    
Hot water services by local electric water storage heaters 118,450 m2 @ 3    
Water services for vending areas Item @ 60,000    
Extra for supplies to retail units Item @ 50,000    
Space heating and air treatment 15,728,000132.786.15%
Gas installation Item @ 175,000    
Low temperature hot water heating installation (including gas-fired boilers) 118,450 m2 @ 22    
Air-conditioning installation: air-handling plant, refrigeration,    
chilled water distribution for four-pipe fan coil installation to offices 118,450 m2 @ 70    
Toilet extract installation 118,450 m2 @ 7    
Smoke extract installation 118,450 m2 @ 12    
Dedicated extract system for external wall void Item @ 1,150,000    
Extra for smoke extract and ventilation to atrium spaces Item @ 600,000    
Car park and loading bay extract ventilation 118,450 m2 @ 3   
Stair/lobby pressurisation Item @ 300,000    
Electrical installations8,329,00070.323.26%
Mains and submains installations 118,450 m2 @ 29    
Power supply to mechanical plant 118,450 m2 @ 4    
Small power installations 118,450 m2 @ 4    
Power and controls for window blinds Item @ 450,000    
Lighting, emergency lighting and small power to landlord’s areas 118,450 m2 @ 15    
Lighting and emergency lighting to basement areas,    
car park and loading bay 7,812 m2 @ 60    
Allowance for enhanced lighting to reception and lift lobbies Item @ 600,000    
Allowance for external lighting Item @ 200,000    
Standby power installation (life safety systems only), including oil system Item @ 450,000    
Lift installations21,090,000178.058.24%
21-person 1600 kg passenger lift 3 m/s serving low-rise floors 8 @ 600,000    
21-person 1600 kg passenger lift 3.5 m/s serving mid-rise floors 8 @ 750,000    
21-person 1600 kg passenger lift 6 m/s serving high-rise floors 8 @ 900,000    
Goods lifts 3000 kg 3.5 m/s serving all floors above ground 2 @ 700,000    
Passenger lift serving car park, doubling as fire-fighting lift 1 @ 150,000    
Fire-fighting lifts serving all floors 2 @ 400,000    
Escalators serving reception and mezzanine 4 @ 110,000    
Car lift 2 @ 150,000    
Protective installations1,939,00016.370.76%
Wet/dry riser installation, with pumps, etc 118,450 m2 @ 1    
Sprinkler installation: common bulk storage, split pump sets 118,450 m2 @ 12    
Hose reels including booster set 118,450 m2 @ 3    
Lightning protection 1 @ 45,000    
Communications installations2,026,00017.100.79%
Fully addressable fire alarm, smoke detection, voice alarm and    
public address systems, interfaced to building management system 118,450 m2 @ 14    
Primary containment for data and communications wiring 118,450 m2 @ 1    
Security: CCTV/detection systems to building perimeter and in car park Item @ 250,000    
Special Installations2,640,00022.291.03%
Building management system 118,450 m2 @ 13    
Complete facade and atrium cleaning installations Item @ 1,000,000    
Communications mast Item @ 100,000    
Builder’s work in connection 2,775,00023.431.08%
Builder’s work in connection with services installations,    
including machine bases, steel stacking framework for double-height    
plant, firestopping, holes, chases, etc (allow 5% of services costs) Item @ 2,775,000    
Preliminaries and contingencies44,850,000378.6417.53%
Construction manager’s pre-construction staff costs Item @ 1,000,000    
Construction manager’s preliminaries, staff costs, overheads    
and profit (allow 15%) Item @ 31,650,000    
Design reserve and construction contingency (allow 5%) Item @ 12,200,000    
Total for shell-and-core construction255,875,0002160.18100%
Category A fit-out
Element costcost/m2 gfa £% of total cost
Based on net internal office area of 74,880 m2   
Wall finishes84,0000.710.26%
Emulsion paint to external walls of cores and to internal columns 16,850 m2 @ 5    
Floor finishes4,568,00038.5614.12%
Medium-grade access floor; fire breaks; dust sealant 74,880 m2 @ 37    
Carpet tiles 74,880 m2 @ 24    
Ceiling finishes3,370,00028.4510.42%
Concealed grid metal tray suspended ceiling to office areas;    
acoustic quilt and fire breaks 74,880 m2 @ 45    
Fittings70,0000.590.22%
Allowance for statutory signage Item @ 70,000    
Space heating and air treatment9,435,00079.6529.17%
Extension of four-pipe fan coil installation into office areas including   
distribution ductwork; fan coil units; grilles and diffusers; insulation;    
condensate drainage; interface with building management system 74,880 m2 @ 126    
Electrical installation5,616,00047.4117.36%
Lighting and emergency lighting to office areas;    
power to fan coil units; supply only floor boxes    
(small power distribution excluded); earthing and bonding 74,880 m2 @ 75    
Communications installation1,123,0009.483.47%
Final connections to fire, smoke detection, alarm and public address systems 74,880 m2 @ 15    
Protective installation1,198,00010.113.70%
Extension of sprinkler installations into office areas (one head per 9 m2) 74,880 m2 @ 16    
Special installations 824,0006.962.55%
Extension of building management system into office areas 74,880 m2 @ 11    
Builder’s work in connection503,0004.251.56%
Allowance for associated builder’s work (say 4% of services costs) Item @ 503,000    
Preliminaries and contingencies 5,550,000 46.8617.16%
Construction manager’s preliminaries, staff costs,    
overheads and profit (allow 15%)  Item @ 4,000,000    
Design reserve and construction contingency (allow 5%) Item @ 1,550,000    
Total for category A fit-out32,341,000273.03100%