- News
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- Building the Future
- Jobs
- Data
- Subscribe
- Events
2024 events calendar
Explore nowBuilding Awards
Keep up to date
- Building Boardroom
All the latest updates on building safety reform
2024 events calendar
Explore nowBuilding Awards
Keep up to dateTable 1: PV technology guide | |||||
Hybrid (mix of monocrystalline & amorphous) | Monocrystalline | Standard polycrystalline | Silicon film & ribbon polycrystalline | Thin film amorphous | |
Typical applications | Modules, especially where space is limited. | Modules, rain screen cladding. Also laminated in glass. | Modules, tiles,slates. Also laminated in glass. | Facades, decorative cladding. | Modules, rain screen, tiles, slates, large roof areas or facades. |
Conversion efficiency at standard test conditions* | 17% to 18.5% | 14% to 16% | 11% to 13% | 9% to 10% | 7% to 8% |
Area needed (m2) per kWp in UK | 6·5 to 7 | 8 to 10 | 11 | 12 | 15 to 18 |
Performance in low or diffuse light conditions | Excellent | Good | Good | Very good | Excellent |
***Installed cost £/kWp | 5000 to 8000 | 5000 to 13000 | 5000 to 13000 | 5000 to 8000 | 4000 to 8000 |
***Installed cost £/m2 | 850 to 1250 | 850 to 1300 | 500 to 1200 | 500 to 700 | 300 to 450 |
**Approximate annual BIPV energy generated (kWh/m2) | 120 to 130 | 75 to 90 | 65 to 70 | 65 | 50 to 60 |
Value of annual BIPV generation (£/m2 @ 5p/kWh) | 6 to 6·5 | 3·75 to 4·5 | 3·25 to 3·5 | 3·25 | 2·5 to 3 |
**Approximate CO2 savings Kg/m2/year | 84 to 91 | 53 to 63 | 46 to 49 | 46 | 35 to 39 |
Environmental impact – embodied energy payback period (years) | Approximately 4 | 4 to 5 | Approximately 4 | 2 to 3 | 0·5 to 2 |
*Standard test conditions are: 25°C, light intensity 1000 W/m2 | |||||
**Estimates based on south-facing installation inclined at 30° to the horizontal. | |||||
***Cost varies widely according to application and installation size. Mass produced modules cost the least, and bespoke laminated glazing the most. Tiles and slates come in between the two extremes, and overall system costs may be reduced depending on any offset due to conventional materials displacement. Economies of scale are generally achieved above 5 kWp. |
Table 2: BIPV project costs | |
Total Capital cost of pv installation | £361 000 |
Total cost per m2 | £241 |
Total cost per kWp | £3540 |
DTI grant | £270 000 |
Operation and maintenance (estimated at £5 per kWp) | £500 pa |
Project costs breakdown | |
PV panels | £238 260 |
Inverters | £28 880 |
Cabling, connections, switchgear | £18 050 |
Framing for pv panels | £21 660 |
Installation | £54 150 |
Project savings | |
Value of energy generated (80 MWh * 5p/kWh) | £4000 pa |
Value of savings through awareness (5% of total) | £150 pa |
Value of ROCs, sold to electricity supplier | £4000 pa |
CO2 saved by bipv generation | 56 tonnes pa |
Note: excludes inflation beyond third quarter 2002; incoming mains electrical service; builder’s work in connection with services; main contractor’s overheads; profit and attendances; main contract preliminaries; professional and prescribed fees; contingencies and design reserve; tax allowances and vat. |