Design issues for specialist space
Libraries and learning resource centres
Design driversSolutions
Continuing expansion of library collectionsGreater use of electronic journals, provision of flexible internal accommodation to allow for growth of hard and soft copy collections
Increasing requirements for group-based workingProvide separate spaces for quiet and group working and special consideration of acoustic management in open-plan areas
Greater use of ITProvide central IT resource areas to reduce network costs and to control noise. Increase space allowances to permit screen and desk working. Provide quiet work space for book-based study
Environmental controlMaximise natural ventilation and daylight where possible. Restrict use of cooling to archive and IT areas only where conditions require it
Research facilities 
Need to attract research scientists and external fundingHigh-quality architecture, high standards of internal and external environment and up-to-date equipment
Facilitation of creative multidisciplinary workingProvision of hierarchy of workplaces to enable group and solo working and range of spaces to encourage interaction
Flexibility to accommodate changeFlexible fit-out and servicing solutions that facilitate replanning and restacking
Separation of undergraduate teaching and graduate research activitiesClear separation of activities either through the development of stand-alone buildings or the internal planning of larger schemes
Laboratories 
Close environmental controlExtensive, high-capacity building services, large ceiling voids, solid floor slabs to control vibration and avoid infestation in floor voids
Quality of working environmentQuality of write-up areas, flexibility of lab space and quality of natural light and air-conditioning systems
FlexibilityModular laboratory design and services distribution, easily accessible services installations, independent structure and services
Security to protect research projects and equipmentPhysical and electronic security measures, balanced against requirements to promote interaction between researchers. Specialist security for animal houses and other high-risk areas
Teaching spaces 
Flexible floorplatesColumn-free space, lightweight partitions, regular planning grid, small power and IT distribution equivalent to commercial office standards to provide flexibility for replanning
High-quality spaceShallow floor plates of 12-15 m for daylight and natural ventilation, clear orientation, use of atriums to provide circulation and social space, use of good-quality, robust materials
Low operational costsNatural ventilation, limited cooling and ventilation for peak lopping only, and use of cost-effective sustainability features
Cost breakdown
Element costcost/m2 gfa £
Substructure 979,000 222.5
Basement construction; excavation and disposal; reinforced insitu concrete ground beams, walls and suspended slab; vapour barrier and protection board; average depth 4.60 m 1300 m2 @ 400  
Piling; 600 diameter; average 35 m long; testing; disposal 48 @ 2500   
Contiguous piling; 450 and 600 diameter; average 17 m long; testing; disposal 190 @ 1400  
Allowance for additional foundation works Item @ 3000   
Allowance for incoming services Item @ 70,000   
Frame and upper floors 718,000163.18
Insitu reinforced concrete columns, core walls and suspended slabs; 400 thick 4000 m2 @ 170  
Extra for exposed trough slab; 400 thick 1450 m2 @ 8   
Structural steel frame; hollow sections at roof level; surface finishes; erection 24t @ 1100   
Roof307,100 69.8
Zinc raised seam roofing; 0.8 mm thick; low pitch; softwood roof members, plywood deck; vapour barrier, insulation 425 m2 @ 130   
Inverted mastic asphalt roof; lightweight screed, average 105 thick; isolating layer; rigid board insulation; gravel ballast, 80 mm thick; including detailing to kerbs for plant and rooflights 495m2 @ 120  
Proprietary opening rooflights; double glazed; Velux; average size 1 m2 32 @ 1000  
Purpose made patent glazing; aluminium glazing bars; sealed double glazed units 280 m2 @ 350  
Allowance for flashings; fascias; sheathing felt etc Item @ 20,000  
Rainwater goods; gutters and roof outlets Item 14,000  
Cleaning gantry Item @ 18,000   
Mansafe system Item @ 5,200   
Pavement rooflights; smoke vents 12 m2 @ 440   
Stairs97,000 22.05
Insitu reinforced concrete stairs and half landings; 1600 wide; 3.7 m average rise 8 @ 4800  
Allowance for balustrades and handrails 190 m @ 140   
Allowance for roof level access ladders 4 @ 3,000   
Allowance for catwalks and platforms in plant rooms Item @ 20,000   
External walls208,500 47.39
Cavity wall construction; facing bricks; blockwork; DPCs; insulation; lintels 345 m2 @ 100   
Cavity wall construction; facing bricks; built against concrete walls; DPCs; insulation; lintels 690 m2 @ 80   
Precast concrete copings 250 m @ 75  
Windows and external doors 301,200 68.45
Proprietary steel-framed, double-glazed windows; polyester powder-coated 75 m2 @ 380  
Curtain walling; steel frame; sealed double-glazed units ; insulated steel-faced spandel panels; polyester powder-coated 470m2 @ 450  
Clerestory windows; sealed double-glazed louvre motorised units; controls 30 m2 @ 900  
External doors; double-glazed, steel-framed doors and doorsets; polyester powder-coated; stainless steel ironmongery 10 @ 1700  
External doors; aluminium louvre doors and doorsets; polyester powder-coated; stainless steel ironmongery 7 @ 800  
Allowance for security shutters Item @ 2000  
Window boards; painted 320 m 30  
Internal walls and partitions160,000 36.36
Partitions; facing blockwork; 150 average thickness (average rate); ancillaries 1340 m2 @ 40  
Extra over for 215 thick blockwork 450 m2 @ 15  
Stud partition; ancillaries; acoustic sealants 1600 m2 @ 50  
Allowance for fire-rated drylining to service risers 360 m2 @ 40  
Cubicle partitions; polyester powder-coated, steel-faced composite panels 12 @ 440   
Internal doors 177,900 40.43
Flush doors; solid core; ply-faced; vision panels; wrot softwood frame; 30/30 fire resistance; stainless steel door furniture; decorations 200 @ 800   
Extra for; oak veneer finish 70 @ 170   
Allowance for borrowed lights Item @ 6000   
Wall finishes 71,600 16.27
Plasterboard wall linings; timber battens; ancillaries 2070 m2 @ 14   
Two-coat plasterwork 1060 m2 @ 10   
Skim coat; to plasterboard 760 m2 @ 4   
Ceramic tiles 100 m2 @ 50   
Painting plaster two coats emulsion paint 8000 m2 @ 3   
Floor finishes348,00079.09
Hardwood flooring; clear lacquer finish 100 m2 @ 80   
Raised access floor; 150 average cavity depth; dust sealer to cavity 2600 m2 @ 50   
Extra for acoustic and fire cavity barriers 2600 m2 @ 5   
Allowance for floor diffusers 260 @ 100  
Allowance for services bridges Item @ 5000  
Screeds; sand cement and proprietary concrete screeds; average 60 thick;   
average rate used 825 m2 @ 20  
Extra for insulation board 140 m2 @ 18  
Carpet tile; to general areas 2900 m2 @ 30  
Rubber tile safety flooring; skirting 210 m2 @ 56   
Rubber sheet flooring; to general areas 680 m2 @ 37   
Floor paint; to plant rooms 390 m2 @ 4   
Softwood skirting; painted 1950 m @ 10   
Ceiling finishes 63,90014.52
Allowance for mats and matwells Item @ 2000   
Suspended ceilings; plasterboard on MF; access panels; paint finish 750 m2 @ 30   
Allowance for radiant panel ceiling Item @ 22,000   
Plasterboard linings; access panels; paint finish 560 m2 @ 20   
Painting; to exposed concrete ribbed soffits; one coat clear sealer 4100 m2 @ 2   
Furniture 307,00069.77
Purpose-made fixed furniture; tables and seating to non-teaching areas Item @ 150,000   
Reception desk Item @ 20,000  
Lecture theatre and seminar room equipment; whiteboards, hanging rails,   
flipcharts and pinboards Item @ 60,000  
Fixed seating to lecture theatre 200 @ 150  
Window blinds 300 m2 @ 50  
Motorised blind to skylight Item @ 5000  
Blackout blinds to teaching spaces Item @ 25,000   
Statutory and orientation signage Item @ 2000   
Sanitary fittings 54,40012.36
WCs, urinals, washhand basins, fittings; cleaners’ sinks; complete (average rate) 80 @ 260   
Extra for fittings for disabled WCs 5 @ 400   
IPS system panels; including access panels; ancillaries 80 m2 @ 200   
Modular washroom units; stainless steel 8 @ 1600   
Hand dryers 14 @ 200   
Disposal installations 103,600 23.55
Rainwater downpipes, outlets and connections to drains 4400 m2 @ 10   
Extra for basement drainage 1300 m2 @ 12   
Waste, soil and vent installation; PVCu pipework and fittings 4400 m2 @ 10   
Water installations 83,400 18.95
Mains water; cold water storage and distribution, water treatment 4400 m2 @ 10   
Hot water installation; calorifiers; distribution; insulation 4400 m2 @ 6   
Local water heaters; distribution; insulation Item @ 13,000   
Space heating and air treatment 583,600 132.64
Boiler; 575 kW, pumpset and pipework in plantroom; flue Item @ 62,000  
Chilled water plant; 260kW; pipework and valves in plantrooms and risers Item @ 49,000  
Air handling units; supply and extract; total mass flow rate 17 kg/s Item @ 82,000  
LTHW distribution pipework; ancillaries; insulation 4400 m2 @ 20  
Chilled water distribution pipework; ancillaries; insulation 1930 m2 @ 10  
Supply and extract ductwork; grilles and diffusers; ancillaries; including allowances for two-hour fire-rated smoke extract ductwork 1930 m2 @ 90  
LTHW heating; trench heating Item @ 26,000  
LTHW heating; panel radiators Item @ 34,000  
Allowance for radiant panel heating and cooling installation to double height spaces 485 m2 @ 40  
Allowance for supplementary cooling to ICT rooms; packaged DX units Item @ 17,000  
Toilet extract installation 4400 m2 @ 3  
Electrical installations 444,500 101.02
Mains and sub – mains installation 4400 m2 @ 20   
Small power installation 4400 m2 @ 20   
Extra over for small power to offices and IT areas; floor outlet boxes 1800 m2 @ 5   
Lighting and luminaires; generally 4400 m2 @ 35   
Extra for enhanced lighting; public spaces and cellular offices 1700 m2 @ 45   
Emergency lighting; generally 4400 m2 @ 5   
Power supply installation to mechanical equipment Item @ 7000   
Gas installation 13,000 2.95
Gas supply to central boiler and kitchen area Item @ 13,000   
Lift installation 86,000 19.55
Four-person electric traction lift serving five floors 2 @ 43000   
Protective installations 22,200 5.05
Lightning protection 4400 m2 @ 2   
Earthing and bonding 4400 m2 @ 1   
Dry riser 1 @ 9000   
Communications installation 152,900 34.75
Fire alarm installation; smoke detectors; call points 4400 m2 @ 15  
Disabled alarm Item @ 3000  
Structured cabling installation; 120% capacity 1250 m2 @ 25  
Security and access control system; intruder alarm 4400 m2 @ 4  
Allowance for CCTV system Item @ 20000  
Telephone and data wireways; for ICT, CCTV and security systems Item @ 15000  
Special installations 110,000 25
Building management system 4400 m2 @ 25   
Builder's work in connection 82,700 18.8
Forming holes, chases etc Allow 5% Item @ 82700   
Preliminaries and contingencies995,800226.32
Testing and commissioning of services; record drawings Item @ 10,000   
Management costs, site establishment and site supervision Allow 13% Item @ 711,800   
Contingency sum Allow 5% Item @ 274,000   
Total construction cost – building only6,471,300 1470.75
Location factors
Inner London1.06
South-east0.97
South-west0.91
East Midlands0.90
West Midlands0.89
East Anglia0.91
Yorkshire and Humberside0.85
North-west0.90
Northern0.86
Scotland0.87
Wales0.85
Northern Ireland0.73
Indicative costs of university buildings
Building type £/m2 gifa
Humanities teaching building 1100 to 1600
Science laboratory buildings 1500 to 2400
Libraries 1300 to 2000
Learning resource centres 1300 to 1800
Lecture theatres 1300 to 1500
Costs are current in fourth quarter 2002, based on a location in outer London. Costs are for the building only, and exclude demolitions, loose furniture and fittings, external works, professional fees and VAT.