Keep up to dateElemental cost analysis (gross internal floor area 558 m2) | |||||
Main element | Breakdown | £ | £/m2 | % | Specification |
Demolitions | demolitions | 24,483.12 | 43.88 | 1.53% | Site clearance and internal alterations |
Substructure | foundations | 109,754.05 | 196.69 | 6.87% | Cast bored insitu piles |
Superstructure | frame | 59,213.55 | 106.12 | 3.71% | Insitu concrete frame |
upper floors | 93,528.15 | 167.61 | 5.85% | Precast tiered floor | |
roofs | 127,043.11 | 227.68 | 7.95% | Standing seam aluminium on steel frame | |
stairs | 0.00 | 0.00 | 0.00% | ||
external walls and cladding | 237,853.43 | 426.26 | 14.89% | Curtain walling and rain screen cladding | |
windows | included in walls | 0.00 | 0.00% | Velfac to temporary reception | |
external doors | 21,781.13 | 39.03 | 1.36% | Automatic revolving door to main entrance | |
internal partitions | 51,108.89 | 91.59 | 3.20% | Blockwork/stud mix – internal glazed screens | |
internal doors | 16,486.24 | 29.55 | 1.03% | Timber doorsets | |
Finishes | walls | 53,711.96 | 96.26 | 3.36% | Acoustic panelling to theatre |
floors | 64,054.04 | 114.79 | 4.01% | Hardwood strip to theatre | |
ceilings | 38,361.65 | 68.75 | 2.40% | Acoustic suspended ceilings | |
Built-in fittings | fixed furniture only | 68,662.41 | 123.05 | 4.30% | Seating to theatre with writing tablets |
Services | sanitary fittings | 5,134.12 | 9.20 | 0.32% | |
services infrastructure | 5,850.83 | 10.49 | 0.37% | ||
disposal installations | 4,603.00 | 8.25 | 0.29% | ||
mechanical services | 161,187.28 | 288.87 | 10.09% | Low-energy displacement ventilation | |
electrical services | 135,466.36 | 242.77 | 8.48% | ||
lift installation | 10,332.90 | 18.52 | 0.65% | Disabled access lifts | |
IT cabling | 17,841.75 | 31.97 | 1.12% | Cabling to theatre seats | |
builders work in connection | 21,418.16 | 38.38 | 1.34% | ||
External works | external finishes and planting | 80,039.15 | 143.44 | 5.01% | Cycle parking |
Drainage | drainage | 17,113.74 | 30.67 | 1.07% | |
external services | 0.00 | 0.00 | 0.00% | ||
Preliminaries | 172,495.87 | 309.13 | 10.80% | ||
Total cost | 1,597,524.87 | 2862.95 | 100.00% | ||
Cost per seat | 8,589 |