Welcome to building.co.uk. This site uses cookies. Read our policy.

Elemental cost analysis for phases one and two, and estimated costs of full laboratory fit-out
Construction summary(costs adjusted for inflation) 
gfa 5,826 m2elemental costcost/m2 gfa% splitnotes
Substructure893,0001937.27%continuous-flight auger-piled foundations
Frame708,0001535.77%insitu reinforced concrete
Upper floors712,0001545.80%flat reinforced concrete slabs 300 mm thick
Roof442,000953.60%terne-coated stainless steel
Stairs111,000240.90%architectural metalwork
External walls1,105,0002389.00%anodised aluminium curtain walling
Windows and external doors74,000160.60%double-glazed anodised aluminium
Internal walls and partitions688,0001485.60%drylined full-height studwork, glazed partitions
Internal doors160,000341.30%laminate-faced and veneered solid-core doors
Wall finishes74,000160.60%skim plaster and emulsion paint
Floor finishes221,000481.80%vinyl sheet, carpeted offices, slate reception
Ceiling finishes172,000371.40%perforated metal ceiling tiles, plasterboard perimeters
Fittings and furnishings553,0001194.50%lab furniture by Byrum
Sanitary appliances37,00080.30% 
Mechanical installation3,777,00081530.76%VAV extract system with some comfort cooling
Electrical installations1,075,0002328.75%power and data to all desks, laboratory benches
Site works181,000391.47%new chemistry square in hard paving with soft landscaping
Drainage23,00050.19%below ground drainage complete with interceptors
External services60,000130.49%new substation and chemical/solvent stores
Preliminaries1,216,0002629.90% 
Total building costs12,279,0002,649100.00%