Keep up to dateCompare and contrast | ||
Lion Plaza | Swiss Re | |
2000 | ||
July 2000 Construction starts | ||
December 2000 Work starts | ||
2001 | ||
September 2001 Steel erection starts | ||
October 2001 Steel erection starts | ||
2002 | ||
September 2002 Steelwork contractor Wescol goes into receivership | ||
November 2002 Topping out ceremony | ||
2003 | ||
June 2003 Last piece of glass installed | ||
Autumn 2003 Handover of shell and core due | ||
December 2003 Interior fit-out due for completion | ||
2004 | ||
March 2004 First tenant, White & Case, due to move in |