| Average bid cost as a proportion of the value of the work to the bidder | ||||
| Full Proposal | Pre-qualification | |||
| Procurement Route | Consultants | Contractors | Consultants | Contractors |
| General Contracting | 5.07% | 0.81% | 3.42% | 0.36% |
| Management | 3.06% | 0.25% | 0.05% | |
| Novated D&B | 4.21% | 0.21% | ||
| Pure D&B 0.47% | 0.80% | 1.05% | ||
| Total | 4.44% | 0.64% | 3.42% | 0.63% |
| Proportion of hours spent on each stage of a bid | ||||
| Lost bid | Won | Lost bids | Won | |
| Consultants | Contractors | |||
| Marketing and pre-bid | 15% | 29% | 22% | 14% |
| Bid/no-bid | 3% | 3% | 7% | 3% |
| Bid mgmt | 14% | 21% | 18% | 31% |
| Proposal prep | 48% | 38% | 27% | 26% |
| Presentation | 19% | 9% | 11% | 15% |
| Review | 2% | 1% | 3% | 3% |
| Averages of responses | ||
| Average | Consultants | Contractors |
| Win ratio | 20% | 20% |
| No. of bids per year | 72 | 164 |
| No. of pre-quals per year | 9 | 59 |
| Project value | £1m | £14m |
| Hours per bid | 136 | 547 |
| Hours per pre-qual | 137 | 474 |
| Cost per bid | £11k | £23k |
| Cost per pre-qual | £8k | £23k |