Table 1: The Tender Process Timetable
CSD minus 14 weeksDate of briefing and issue of the invitation to tender
CSD minus 13 weeksThe date ‘window’ for tender company site visits
CSD minus 11 weeksDate of submission of bids
CSD minus 10 weeksDate for notification of inclusion in the final short list, and notification of any failed bids
CSD minus 8 weeksStart of the bid assessment period
CSD minus 6 weeksContract award announcement dates
CSDContract start date
(*CSD: Contract start date)