Welcome to building.co.uk. This site uses cookies. Read our policy.

Robert Clack School sports hall elemental cost breakdown
Element Total cost £Cost £/m2% total cost
Substructure 223,198 98.72 5.45
Superstructure   
Frame 149,842 66.27 3.66
Upper floors 5,631 2.49 0.14
Roof 324,971 143.73 7.93
Stairs 1,157 0.51 0.03
External walls 418,078 184.91 10.20
Windows and external doors 88,577 39.18 2.16
Internal walls and partitions 193,369 85.52 4.72
Internal doors 41,369 18.30 1.01
Internal finishes   
Wall finishes 203,121 89.84 4.96
Floor finishes 159,138 70.38 3.88
Ceiling finishes 12,803 5.66 0.31
Fittings and furnishings 339,577 150.19 8.29
Services   
Sanitary appliances 23,815 10.53 0.58
Disposal and water installations 123,068 54.43 3.00
Space heating and air treatment 254,685 112.64 6.22
Electrical installations 236,176 104.46 5.76
Protective and communication installations47,000 20.79 1.15
Builder’s work in connection 8,027 3.55 0.20
External works 819,611 362.50 20.00 Preliminaries
Contingencies 70,850 31.34 1.73
Total 4,097,163 1,812.11 100.00
Gross floor area 2261 m2.    
Tender prices of June 2002, excluding professional fees, VAT and client fittings.