- News
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- Building the Future
- Jobs
- Data
- Subscribe
- Events
2024 events calendar
Explore nowBuilding Awards
Keep up to date
- Building Boardroom
All the latest updates on building safety reform
2024 events calendar
Explore nowBuilding Awards
Keep up to dateApartment shell and core – cost breakdown | |||
£ element cost | £/m2 gross internal floor area | % of total cost | |
Substructure | 595,000 | 85.00 | 8.51 |
Substructure, piled foundations, pile caps, ground slab, site excavation and disposal, dewatering etc 1000 m2 @ 550 | |||
Allowance for drainage 1000 m2 @ 35 | |||
Allowance for lift pits etc 2 @ 5000 | |||
Frame and upper floors | 1,322,500 | 188.93 | 18.93 |
Insitu reinforced concrete frame and upper floors, 250 mm thick slabs, 225 mm blade columns, allowance for forming openings 6650 m2 @ 150 | |||
Balconies, primary and secondary frame, decking, balustrading 65 @ 5000 | |||
Roof | 120,800 | 17.26 | 1.73 |
Flat roof coverings, single ply membrane, insulation, ballast; allowance for details to upstands 1000 m2 @ 75 | |||
Extra for roof terraces and paving to terraces 350 m2 @ 45 | |||
Allowance for roof drainage, roof sundries 1000 m2 @ 15 | |||
Roof access equipment, latchways, cat ladder, access hatch, safety balustrade Item @ 15,000 | |||
Stairs | 144,000 | 20.57 | 2.06 |
RC concrete stairs, mild steel balustrades and handrails, carpet to treads/risers 14 @ 7000 | |||
Extra over for enhanced finishes to entrance level staircases 2 @ 5000 | |||
Balustrade and parapet to terraces; polyester powder coated steel 120 m @ 300 | |||
External walls, windows and doors | 1,866,000 | 266.57 | 26.70 |
Unitised curtain walling; polyester powder coated insulated aluminum spandrel panels; sealed double-glazed tilt and turn windows 4000 m2 @ 450 | |||
Extra for doors to balconies, allowance for single leaf doors, ironmongery 65 @ 800 | |||
Entrance doors, aluminium framed glazed door and screen 1 @ 10000 | |||
External fire escape doors, metal, polyester powder coated finish to match curtain walling 2 @ 2000 | |||
Internal walls and partitions | 287,000 | 41.00 | 4.11 |
Core walls, insitu concrete, 225 thick 420 m2 @ 100 | |||
Party walls to apartments and corridors; dense concrete block to comply with Building Regulations Part E; head restraint, fire stopping 4900 m2 @ 50 | |||
Internal doors | 135,000 | 19.29 | 1.93 |
Fire doors to cores and corridors; hardwood architraves/frames, including basic ironmongery 60 @ 750 | |||
Fire doors to risers; hardwood architraves / frames, including basic ironmongery 20 @ 500 | |||
Apartment entrance doors; solid core doors, hardwood architraves/frames, including basic quality security ironmongery 100 @ 800 | |||
Wall finishes | 90,000 | 12.86 | 1.29 |
Plasterboard to concrete and blockwork, with specialist painted finish; entrance hall 500 m2 @ 50 | |||
Plasterboard to concrete and blockwork, with emulsion paint finish; lift lobbies and corridors 2600 m2 @ 25 | |||
Floor finishes | 94,100 | 13.44 | 1.35 |
Feature ceramic floor tiles, sand cement screed; entrance hall 50 m2 @ 120 | |||
Heavy duty carpet, sand cement screed; corridors 1050 m2 @ 60 | |||
Ceramic tile, sand cement screed; lift lobbies 170 m2 @ 100 | |||
Skirtings, surface fixed skirting, painted mdf 810 m @ 10 | |||
Ceiling finishes | 41,600 | 5.94 | 0.60 |
Painted plasterboard with feature bulkheads; reception 50 m2 @ 100 | |||
Painted plasterboard on battens; lift lobbies and corridors 1220 m2 @ 30 | |||
Furniture and fittings | 15,000 | 2.14 | 0.21 |
Allowance for reception area fittings; mailboxes, signage, mats and matwells, artwork Item @ 15,000 | |||
Sanitary fittings | 7,000 | 1.00 | 0.10 |
Allowance for cleaners sinks 14 @ 500 | |||
Disposal installations | 98,000 | 14.00 | 1.40 |
Allowance for rainwater disposal; downpipes and connections to below-ground drainage 7000 m2 @ 3 | |||
Allowance for soil, waste and overflow installations; stacks and connections to below-ground drainage 7000 m2 @ 11 | |||
Water installations | 125,700 | 17.96 | 1.80 |
Allowance for cold water storage tanks, booster pumps, mains distribution pipework, trace heating, water softener/conditioner etc 7000 m2 @ 15 | |||
Hot and cold water services to landlord’s areas, including local water storage heaters 1220 m2 @ 17 | |||
Space heating and ventilation | 161,200 | 23.03 | 2.31 |
Electric panel heaters; landlord’s areas 1220 m2 @ 3 | |||
Central extract system for bathrooms; ductwork, extract fans 7000 m2 @ 20 | |||
Reception area air treatment Item @ 7500 | |||
Supply and extract; plantroom areas Item @ 10000 | |||
Electrical installations | 177,900 | 25.41 | 2.55 |
Allowance for mains switchgear, cabling, containment and landlord’s distribution boards 7000 m2 @ 10 | |||
Small power; landlord’s areas 1220 m2 @ 6 | |||
Power supply to mechanical services 7000 m2 @ 5 | |||
Lighting installation to landlord’s areas, including emergency lighting 1220 m2 @ 30 | |||
Feature lighting to entrances Item @ 15000 | |||
Earthing and bonding 7000 m2 @ 2 | |||
Lift installation | 180,000 | 25.71 | 2.58 |
Lift installation; 13-person firefighting lifts serving seven storeys 2 @ 90000 | |||
Protective installations | 50,600 | 7.23 | 0.72 |
Allowance for dry riser inlets 1220 m2 @ 30 | |||
Lightning protection 7000 m2 @ 2 | |||
Communications installations | 123,700 | 17.67 | 1.77 |
Allowance for fire alarm system to landlord’s areas 1220 m2 @ 35 | |||
Allowance for telephone containment only 7000 m2 @ 4 | |||
Allowance for TV/Satellite system; central aerial and distribution 7000 m2 @ 4 | |||
Allowance for CCTV and access control to perimeter Item @ 25000 | |||
Special Installations | 28,000 | 4.00 | 0.40 |
Allowance for localised controls for cold water system 7000 m2 @ 4 | |||
Builder’s work in connection | 48,000 | 6.86 | 0.69 |
Forming holes and chases; firestopping. Allow 5% Item @ 48000 | |||
Preliminaries and contingencies | 1,276,000 | 182.29 | 18.26 |
Testing and commissioning of building services installations. Allow 2.5% of services cost Item @ 25000 | |||
Contractor’s overheads, site establishment and site supervision, excluding design fees. Allow 16% Item @ 918000 | |||
Design reserve and contingency. Allow 5% Item @ 333000 | |||
Total shell-and-core cost | 6,987,100 | 998.16 | 100.00 |
Total shell-and-core cost (£/m2 net saleable floor area) | 1,249.93 |